To avoid these ads, REGISTER NOW!

New 25x28 Garage project rollin'!

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Things have been in motion for a few weeks, but I've waited to start a thread on my Garage/Shop project until now. I'm putting up a 25x28 detached garage, 2x6x10 foot walls, scissor trusses, radiant floor heat (laid out for future installation of a 2 post lift).

25x28 is the biggest I can fit to meet the required setbacks from the property lines and the denitrification lines from the septic system. I had originally planned for a 24x24, but ended up upgrading...

Now for the pictures!


Location laid out, fence removed:
Garage0008.jpg



Footings dug out:
Garage0014.jpg

Garage0016.jpg



Forms and gravel installed!:
Garage0018.jpg

Garage0019.jpg

Garage0021.jpg
 
To avoid these ads, REGISTER NOW!
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
We'll be pouring a monolithic slab 5" deep, with 20" footings, 8" above grade. Vapor barrier over the gravel, 1/2" styrofoam over that, then mesh and radiant tubing:

Insulation installed:
Garage0024.jpg

(Green squares mark radiant tubing setback for future lift)
Garage0026.jpg




Radiant tubing installed:
This isn't very common here in NC, so it's a first time experience for my contractor and concrete guys, (the plumber doing the install has experience though) Everyone's done great so far!
Garage0027.jpg


Garage0028.jpg


Garage0031.jpg


Garage0032.jpg
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Tubing was installed on Monday, pressure tested Tuesday, inspection was on Wednesday (passed!) and concrete pour was Thursday: :beer:

Garage0036.jpg


Garage0038.jpg


Garage0040.jpg


Garage0041.jpg


Garage0043.jpg


Now I need to water it 3 times a day for a few days... then we put walls up!

Garage0044.jpg



Updates to follow!!
 

JMURiz

Well-known member
Joined
Dec 6, 2005
Messages
1,483
Location
NoVA
Looking good!
Wish someone would have told me to keep mine damp while it set-up...now I have some hairline cracks, oh well hindsight is 20/20.
 

Kevin54

MEMBER EMERITUS
Joined
Jan 12, 2005
Messages
29,341
Location
Urbana, Ohio
Too bad you couldn't have went with 26'. A 25' wide garage is going to cost you extra money. Trusses will have to be made special unless you go with rafter, you will have extra cost or waste in sheeting because it is now a ******* size (not 2' increments) in both the roof and in the sidewalls, plus calculating studding for door openings etc. How do I know? Been there, done that. A contractor screwed my sons' footers up and had to go an extra foot. 25' front to back really screws up rafter spans.

Kevin
 

cyclopsblown34

Well-known member
Joined
Jan 26, 2007
Messages
597
Location
Russellville, Missouri
Killer build, I am astounded at how many people are as fanatical about their garages as me. Is the neighbor going to remove the carport once your shop is up? It might be an eyesore once your shop is complete.
 

curlyws6

Well-known member
Joined
Mar 7, 2007
Messages
112
Location
Eastern North Carolina
I bet you're getting excited seeing it actually moving along (I know I was when I came home the first day and found the footing survey for my garage :) ).
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Been a while, and I was out of town for the past week. But a few more progress pictures to pass along:

Building supplies have been delivered:

Garage0046Medium.jpg


Garage0046Medium.jpg


Trusses and the LVL beam for the header above the garage door should be delivered this week.
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Work on the walls has begun! Hopefully we'll get the first one standing up tomorrow.

Garage0047Medium.jpg


Garage0048Medium.jpg


Garage0049Medium.jpg


Garage0050Medium.jpg



I'd have liked to go with a 26' deep garage, unfortunately I'm restricted by the lateral lines of my septic field and the setbacks associated with them. Because the garage must sit behind the back line of the house to allow me to build 5' from the property line, and the lateral lines require a 10' setback, and sit 36 feet behind the house, I'm really as large as I can possibly build. I should really scan and post the drawing of the site so you can see what I'm talking about.

More pictures this week!!:beer:
 

Will67

Well-known member
Joined
Nov 17, 2006
Messages
852
Location
Hell's half acre
I hope this doesn't turn into a thread highjack...

I have been looking at every garage thread looking for ideas, and am amazed at the differences in building codes that manifest in differences in footings, shear-walls, anchors, etc...

I was looking at you footing/slab and ask myself were are the huricane anchors or J-bolts. I live in California seismic activity is always at the back of your mind and is a big part of building codes. It looks like you "mud-sill" is shot down with____.
 

Steve in Mi

Well-known member
Joined
Mar 13, 2007
Messages
1,042
Location
Mid Michigan
Will67, you're not alone in the observation of different foundation treatments. The presence of "J" bolts and perimeter re-rod is the norm in my local area.

It does appear to have drilled holes for anchors in post #11.
 
Last edited:
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Will67, you're not alone in the observation of different foundation treatments. The presence of "J" bolts and perimeter re-rod is the norm in my local area.

It does appear to have drilled holes for anchors in post #11.

There are indeed holes drilled for anchors. The holes are about 3" deep and 1/2" in diameter, spaced about 44" apart.

I've also noted the differences in foundations. A lot of people building north of me seem to be pouring footings, then setting concrete block and doing a separate slab pour. Monolithic (footings in slab) pours are the standard around here, I suppose that's because our climate is warmer than our friends up north?
 

99E36M

Well-known member
Joined
Jan 3, 2007
Messages
67
There are indeed holes drilled for anchors. The holes are about 3" deep and 1/2" in diameter, spaced about 44" apart.

I've also noted the differences in foundations. A lot of people building north of me seem to be pouring footings, then setting concrete block and doing a separate slab pour. Monolithic (footings in slab) pours are the standard around here, I suppose that's because our climate is warmer than our friends up north?

Yup, slabs up here in MA require a 2' deep frost wall. Good thing concrete is cheap....oh wait....
________
Peak Towers Condominium Pattaya
 
Last edited:
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Trusses and the LVL's for the header above the garage door arrived today!

Garage0051.jpg


Garage0052.jpg
 

64auto

Well-known member
Joined
May 22, 2007
Messages
58
Looking good. I am getting ready to pour my floor. How long should I wait before I start To water after it is poured? Just don't want to leave spots in it from the sprinkler and water.
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Looking good. I am getting ready to pour my floor. How long should I wait before I start To water after it is poured? Just don't want to leave spots in it from the sprinkler and water.

My concrete guys had finished up by about lunchtime, and had me water the slab for about 30 minutes at about 6pm. Ask your concrete contractor for specific directions for your pour.
 

StingRay

Well-known member
Joined
Jan 26, 2006
Messages
1,340
Location
Saskatoon,SK. Canada
Funny how building codes are different. Up here where cold takes on a whole new meaning a monolithic pour with 10" wide and 10 inch deep edges is pretty normal. Here frost goes down 7 feet. You have to go 8 feet to keep water lines from freezing. I've never seen a slab fail from heaving either. I've seen lots of basement floors heave up from excessive water under the slab though.

J bolts and hurricane clips are pretty much unheard of too. We do get tornados occsionally and I've seen 60-70 mph plow winds but we don't seem to worry much about things blowing away. I'm sure some use good hardware but as I understand it all the code requires to anchor the trusses down is 3 nails toe nailed into the top plate. I find it kind of scarey but my garage is built just so..... and not by me.
 
Last edited:
To avoid these ads, REGISTER NOW!
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
More walls up today:

Garage0055.jpg


Garage0056.jpg


Garage0057.jpg


The guys have been working from about 7:30 am until noon or so, after that it's just been too hot to do much outside if you can avoid it. Cooler weather forcasted for next week however!
 

wmonroe

Well-known member
Joined
Oct 5, 2006
Messages
229
Location
Near Pittsburgh, PA
The garage is coming along great. Seeing how fast your and other peoples garages are progressing sometimes make me wish I would have hired someone to do mine instead of doing it myself.:beer:
Will
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Got the rest of the walls up, and the sheathing almost finished! Trusses should start on Monday!

Garage0058.jpg


Garage0059.jpg


Garage0061.jpg
 

V-10 Killer

Well-known member
Joined
Feb 11, 2007
Messages
1,011
Location
Midland, MI
Just out of curiousity, why did you leave the top plate unsheathed?
I've just put up 8' of OSB and have 2' 7" left to the top of the top plate. I was going to run it up over the energy heel on the trusses.
 

V-10 Killer

Well-known member
Joined
Feb 11, 2007
Messages
1,011
Location
Midland, MI
Aah, strike that last post, I bet you're using 92 5/8" precut studs aren't you. almost 2" overlap onto the slab leaves 2" short up top.

Sometimes I have to say it out loud before I can actually understand it...
 

IdahoJoe

Well-known member
Joined
Dec 11, 2005
Messages
46
Location
Bear Creek, WA. It's near Seattle.
... I'm putting up a 25x28 detached garage, 2x6x10 foot walls, scissor trusses, radiant floor heat...

Aah, strike that last post, I bet you're using 92 5/8" precut studs aren't you....

I don't think he's using 92 5/8" studs for a 10 foot sidewall...at least not looking through the overhead door to the back wall...
 
Last edited:

V-10 Killer

Well-known member
Joined
Feb 11, 2007
Messages
1,011
Location
Midland, MI
It looked tall to me too, but look at the service door opening. Its rough opening is probably 6' 9" tall, plus a 12" header plus around 2' more to the top of the top plate.

But you're right in the quote, I didn't see that he stated 2x6 10' studs.
 

V-10 Killer

Well-known member
Joined
Feb 11, 2007
Messages
1,011
Location
Midland, MI
Hahaha, I just reread my last post and added up the numbers, yep that's about 10'.....

Ok, I'm gonna be quiet now, I have 4 posts on this page, and 3 of them are garbage:lol_hitti
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
To reply to the raised questions:

Yes, they are 2x6x10' sidewalls, hence the gap in sheathing up top. The back and front walls have now been fully sheathed (pictures coming in a minute). The gable ends will be on the side walls to match the construction of the house.

Not quite sure why he didn't wait to put the sheathing on the side walls since he'll have to go all the way up to the gables eventually, but as long as it gets done, it doesn't much matter to me. That's the nice part about paying someone else to do it. :thumbup:

For reference, that is an 18x8' opening for the garage door.

Yes, that's my VW bus. Gotta have a nice climate-controlled place to work on it, right?:beer:
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
Today's picture:

Sheathing is finished, getting ready to start putting trusses up!

Garage0063.jpg
 

great adventure

Well-known member
Joined
Mar 2, 2006
Messages
89
Location
kingdom of bahrain
very good job....
may I ask you one question

could you please tell me why you put the red hoses under the
concreat...?? and connected them with a gauge??

thank you:thumbup:
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
looks good

what is the pitch of the roof and the pitch of the vault?

Originally it was to be 5/12 roof to match the house, and 3/12 on the inside, that got changed to 6/12 and I believe 4/12 on the inside for extra clearance... didn't know about that change until after the trusses arrived on site, :headscrat but oh well.
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
very good job....
may I ask you one question

could you please tell me why you put the red hoses under the
concreat...?? and connected them with a gauge??

thank you:thumbup:

The red tubing is for radiant floor heating. It was pressurized during the pour to make sure there was no damage (and leaks) to the tubing.
 
OP
N

Namocsid

Well-known member
Joined
Jan 18, 2007
Messages
151
The rest of the trusses went up today. Sheathing will be finished tomorrow!

Garage0072.jpg


Garage0073.jpg


Garage0075.jpg
 
To avoid these ads, REGISTER NOW!
Top Bottom