I'm getting ready to put up a 30'x40' post frame building.
Due to local politics, this is the only portion of my property that I will be able to build my planned shop. (Without rezoning, survey, paperwork, delays, etc...)
In the pictures, the shop will extend from the front of the mower deck all the way to where it slopes up again in the back, and three feet offset from the field on the left side.
As you can see in the pictures, the site is currently sloped. The most significant would require approximately 3' of fill to bring it to grade. What does everyone suggest for footer/footings? Would fill and slab be sufficient, or am I in poured wall/block foundation territory?
Due to local politics, this is the only portion of my property that I will be able to build my planned shop. (Without rezoning, survey, paperwork, delays, etc...)
In the pictures, the shop will extend from the front of the mower deck all the way to where it slopes up again in the back, and three feet offset from the field on the left side.
As you can see in the pictures, the site is currently sloped. The most significant would require approximately 3' of fill to bring it to grade. What does everyone suggest for footer/footings? Would fill and slab be sufficient, or am I in poured wall/block foundation territory?