vision8
Well-known member
Getting ready to pour my 3/4" pex heated concrete floor in a 30' x 50' x 16 ' all steel prefab shed , no windows but have two 10' x 10' OHDs , a 8' x8' OHD and a 4' x 7' man door with a poured 10" x 4' foundation . Work shop area will be 35' x 30' area with a 9,000 lb Rotary 2 post hoist; a OLD Lathe 14' ways and 20" chuck ; a Small Bridgeport Mill; maybe a 2 ton free standing jib to service these in the future ?
Retirement Useage: I do Vintage motorcycle and Vintage Car restoration.
Had a contractor quote to pour a 6" floating slab inside the 2" insulated interior foundation walls ( 2" x 48" outside insulation , down to the weeping tile, no water has penetrated the foundation so far ). No concrete over the doorway entrances to allow for settling of the 2 year old interior fill which is covered by 6" of clear 3/4" gravel.
This contractor does not use rebar only wire mesh because of the thermal expansion of rebar promotes cracking in my Southern Ontario, Canada weather zone and bubble wrap for vapour barrier and no insulation then does 8' x8' cuts !
I was looking to put 6" of clear 3/4" gravel then 2' x 4' x 1.5" blue sytrofoam used sheets and a 50 Mil vapour barrier ; 1/8" wire mesh for pex spacing , two loops per zone , six zones in total around the exterior of the floor to provide a 50 - 55 degree temperature from a 60,000 BTU natural gas boiler system and then the 1/2" rebar at 2' x 2' spacing for strength.
If I do all the prep , I have a quote of $7,000 to pour the slab only; the contractor wants double this to do the wire mesh pour !
What would you do if this was your clean sheet to proceed ?
What thickness for the slab ?
Al in Southern Ontario
Retirement Useage: I do Vintage motorcycle and Vintage Car restoration.
Had a contractor quote to pour a 6" floating slab inside the 2" insulated interior foundation walls ( 2" x 48" outside insulation , down to the weeping tile, no water has penetrated the foundation so far ). No concrete over the doorway entrances to allow for settling of the 2 year old interior fill which is covered by 6" of clear 3/4" gravel.
This contractor does not use rebar only wire mesh because of the thermal expansion of rebar promotes cracking in my Southern Ontario, Canada weather zone and bubble wrap for vapour barrier and no insulation then does 8' x8' cuts !
I was looking to put 6" of clear 3/4" gravel then 2' x 4' x 1.5" blue sytrofoam used sheets and a 50 Mil vapour barrier ; 1/8" wire mesh for pex spacing , two loops per zone , six zones in total around the exterior of the floor to provide a 50 - 55 degree temperature from a 60,000 BTU natural gas boiler system and then the 1/2" rebar at 2' x 2' spacing for strength.
If I do all the prep , I have a quote of $7,000 to pour the slab only; the contractor wants double this to do the wire mesh pour !
What would you do if this was your clean sheet to proceed ?
What thickness for the slab ?

Al in Southern Ontario
