homeputter
Active member
- Joined
- Dec 29, 2011
- Messages
- 26
My 24'x24' garage is almost done, but there were a lot of tense moments along the way. Fortunately, I had a great contractor.
First, I complained that the re-inforcement bars were laying on the ground and did not have chairs under them before the pour. "Oh, they lift those up while pouring the concrete." I watched while the workers tried to lift the bars up and then the guy leveling the concrete would walk over that area and push them back down. I told the contractor those bars are now laying on the ground. He said " Do you want me to tell them to go over and pull the bars up?" Like how are they going to do that while walking all over the place trying to level the concrete?! Does everyone in residential construction just lay the rebar on the ground and hope it is pulled up to the middle?
Then when the slab was poured and they RAN OUT OF CONCRETE! The contractor was trying to order another truck, but didn't know how long it would be - 45 minutes up mountain from concrete plant minumum probably a couple of hours. I told them to cancel another truck they would just have to concrete cut the rough edges later. I did not want a cold joint.
Next the roof trusses arrived and did not have the 30" overhang I specified. I told the contractor I paid for 30" overhang and that is what I wanted. Fortunately, the lead carpenter showed me if they doubled the facia boards, it would give me the 30"
I made sure when they poured the the garage apron later (and the 30 sq ft in the garage where they ran out of concrete) they had chairs under the rebar. That pour went much smoother since they workers did not have to fool around pretending to lift up the rebar.
Now the garage is almost done and the concrete looks great. The contractor did a great job of using the saw cuts to incorporate the patched area so you can't tell the area where they ran out of concrete.
The funny thing is the concrete contractor insisted on ordering the concrete the 2nd time (instead of the general contractor) and HE almost ran out. On the 6 yard pour, there was less than 1 cu ft of concrete left over. He said "well, I have been doing this for 30 years." I said "you still called that too close."
I specified that the concrete had fiber in it, 4" slump max and that plastisizers were to be used to get the slump the concrete guy wanted but no extra water was to be added.
The finished concrete slab looks really good and so far NO cracks - even hair line.
Next when the hardi-board above the garage door was installed, the seams did not line up with the hardi-board below. I called the contractor and fortunately, he said "that does not meet my standards and it will be fixed." This was 6 pm. 15 minutes later the framing company owner and the lead carpenter were having a shouting match in my driveway. I heard the lead carpenter yelling "SO THE OWNER IS ALWAYS RIGHT?!! The owner replied and "now we are yelling in front of the owner and I don't like it." They retired to the street and talked quietly for another 20 minutes. The next day the upper siding was removed and re-installed right. WHEW.
There is now only the french drains around the foundation, stem wall waterproof membrane and back filling left to do. That will happen this week.
After going through all of this, I have to say I am delighted with the final result but I had a few sleepless nights.
I will post pictures later.
First, I complained that the re-inforcement bars were laying on the ground and did not have chairs under them before the pour. "Oh, they lift those up while pouring the concrete." I watched while the workers tried to lift the bars up and then the guy leveling the concrete would walk over that area and push them back down. I told the contractor those bars are now laying on the ground. He said " Do you want me to tell them to go over and pull the bars up?" Like how are they going to do that while walking all over the place trying to level the concrete?! Does everyone in residential construction just lay the rebar on the ground and hope it is pulled up to the middle?
Then when the slab was poured and they RAN OUT OF CONCRETE! The contractor was trying to order another truck, but didn't know how long it would be - 45 minutes up mountain from concrete plant minumum probably a couple of hours. I told them to cancel another truck they would just have to concrete cut the rough edges later. I did not want a cold joint.
Next the roof trusses arrived and did not have the 30" overhang I specified. I told the contractor I paid for 30" overhang and that is what I wanted. Fortunately, the lead carpenter showed me if they doubled the facia boards, it would give me the 30"
I made sure when they poured the the garage apron later (and the 30 sq ft in the garage where they ran out of concrete) they had chairs under the rebar. That pour went much smoother since they workers did not have to fool around pretending to lift up the rebar.
Now the garage is almost done and the concrete looks great. The contractor did a great job of using the saw cuts to incorporate the patched area so you can't tell the area where they ran out of concrete.
The funny thing is the concrete contractor insisted on ordering the concrete the 2nd time (instead of the general contractor) and HE almost ran out. On the 6 yard pour, there was less than 1 cu ft of concrete left over. He said "well, I have been doing this for 30 years." I said "you still called that too close."
I specified that the concrete had fiber in it, 4" slump max and that plastisizers were to be used to get the slump the concrete guy wanted but no extra water was to be added.
The finished concrete slab looks really good and so far NO cracks - even hair line.
Next when the hardi-board above the garage door was installed, the seams did not line up with the hardi-board below. I called the contractor and fortunately, he said "that does not meet my standards and it will be fixed." This was 6 pm. 15 minutes later the framing company owner and the lead carpenter were having a shouting match in my driveway. I heard the lead carpenter yelling "SO THE OWNER IS ALWAYS RIGHT?!! The owner replied and "now we are yelling in front of the owner and I don't like it." They retired to the street and talked quietly for another 20 minutes. The next day the upper siding was removed and re-installed right. WHEW.
There is now only the french drains around the foundation, stem wall waterproof membrane and back filling left to do. That will happen this week.
After going through all of this, I have to say I am delighted with the final result but I had a few sleepless nights.
I will post pictures later.

