Kevin C
Well-known member
I have the epoxy kits and it looks like the weather is close to cooperating.
When I had the floor poured I told the contractor that I was planning on using an Epoxy coating. He commented that he would not finish it quite so finely, so as to leave a bit more open texture for better adhesion.
So one option would be to power wash, etch and put the epoxy down.
That said, their are a couple of very light trowel marks and since I'm not planning on using chips I though that some further surface prep may help.
For a couple of dollars I can rent a buffer and an attachment that allows me to use giant 80 grit sanding disks. I was planning on spending a couple of hours or so and sanding the entire floor before I acid etch it.
http://www.homedepotrents.com/proTools/floor_maintainer.asp?cm_sp=tool_rental-_-left_nav-_-floor_maintainer
I dont think I want to or need to go as far as a full diamond grind....
Next question: In the process of framing the place, I dropped my hammer a couple of times. Small chips, not too bad. Should I fill them or will the epoxy-coat be enough to minimize the defects?
Final question: My contractor troweled grooves in the pad and then saw cut them a bit deeper for crack control. They look good but I'm not sure if I should caulk them or not. If I leave them open do I detail them in with a paint brush? I dont think it would be good to have them end up partially filled with epoxy.
Thanks,
Kevin
When I had the floor poured I told the contractor that I was planning on using an Epoxy coating. He commented that he would not finish it quite so finely, so as to leave a bit more open texture for better adhesion.
So one option would be to power wash, etch and put the epoxy down.
That said, their are a couple of very light trowel marks and since I'm not planning on using chips I though that some further surface prep may help.
For a couple of dollars I can rent a buffer and an attachment that allows me to use giant 80 grit sanding disks. I was planning on spending a couple of hours or so and sanding the entire floor before I acid etch it.
http://www.homedepotrents.com/proTools/floor_maintainer.asp?cm_sp=tool_rental-_-left_nav-_-floor_maintainer
I dont think I want to or need to go as far as a full diamond grind....
Next question: In the process of framing the place, I dropped my hammer a couple of times. Small chips, not too bad. Should I fill them or will the epoxy-coat be enough to minimize the defects?
Final question: My contractor troweled grooves in the pad and then saw cut them a bit deeper for crack control. They look good but I'm not sure if I should caulk them or not. If I leave them open do I detail them in with a paint brush? I dont think it would be good to have them end up partially filled with epoxy.
Thanks,
Kevin