Building a new 30x40 shop and at this point I have poured frost walls and insulated 4' down in preperation for a heated floor.
This is where I am confused...I have backfilled leaving 2" below the door cut outs to install 2" of insulation under the poured floor and extended the insulation 5" up the walls for the poured floor therefore the floor will extend through the openings uninsulated??
Hope I am fairly clear on this??
So not sure about this portion of the floor extending outside the heated area and what I am going to lose??
My good friend kept the floor flush to the cut outs leaving the insulation exposed at the door and place polymer strips over it.
Should I remove fill and pour flush???
Think I need a beer
New to the site and seems there is a wealth of knowledge on here..
Building a new 30x40 shop and at this point I have poured frost walls and insulated 4' down in preperation for a heated floor.
This is where I am confused...I have backfilled leaving 2" below the door cut outs to install 2" of insulation under the poured floor and extended the insulation 5" up the walls for the poured floor therefore the floor will extend through the openings uninsulated??
Hope I am fairly clear on this??
So not sure about this portion of the floor extending outside the heated area and what I am going to lose??
My good friend kept the floor flush to the cut outs leaving the insulation exposed at the door and place polymer strips over it.
Should I remove fill and pour flush???