We were contracted to erect the building and an office inside. This is going to house equipment and tanks for a water filtration plant at a landfill. There will be two large tanks at the outside end of the building with a catwalk, hence the high door.
It is 50' x 75' x 24' at the eave. Had to be tall to accommodate tanks inside the building.
It is def more expensive than a pole barn, but surprisingly the building itself was fairly reasonable. The GC purchased it, he told me it was in the 50k range.
Keep in mind that is steel and insulation only. Concrete, footing work, and installation labor will easily double that cost though.