Chris705
Well-known member
As I prepare to install PEX tubing in my concrete slab (40'x44' overall size) I have been reading as many manufacturers web sites as I can on the topic. I have also read with great interest the many posts here on GJ about radiant slab heating. I have a couple questions that I cannot find answers to.
I will point out that my intention is to use 3” blueboard insulation under the slab and 1” at slab edge. I plan on using the 6x6 wwm as a tubing layout guide and hold-down with zip ties. I don’t plan on pulling the wwm up or add other reinforcing other than micro-fibers to help w/ shrinkage cracks. I do plan on three saw cuts in each direction on the monolithic pour.
1) In Viega’s site as well as seeing the same thought elsewhere….. I see the installation recommendation about bridging construction (cold) joints and control (saw cut) joints. The Viega site recommends bridging and protecting the PEX tubing of any planned joint (both cold and saw cut joints) with 12” of rigid pvc tubing. So first question is has anyone ever experienced any problems with their tubing installation and use by NOT doing this at joints? I assume for the most part no one does this?
2) My current garage slab design has 7 loops of ½” PEX at 250’ length. I also intend to eventually incorporate future snow melting of a long sloped sidewalk and short concrete drive……I need to install the supply and return lines of these future 4 loops to the edge of the foundation wall and will eventually install the actual in slab PEX at a latter date. The PEX layout for snowmelt again has runs equaling 250’ length at foundation edge and I intend to use ½” PEX. I will run these four loop feeds under my garage slab to where I will eventually tie them into the snow melt and will insulate them for the approx. 50’ they will run under my slab (this makes the tubing runs 300' long). The snowmelt will be on its own zone for manual control. Second question – is there any benefit to insulating the snowmelt PEX as it runs under my garage slab? AND also is there any benefit to using a larger dia. PEX (5/8 or ¾) for this portion (I ask this because I mentioned the long sidewalk will slope…. about 20’ vertical over 125’ run).
Thanks for any and all input!
I will point out that my intention is to use 3” blueboard insulation under the slab and 1” at slab edge. I plan on using the 6x6 wwm as a tubing layout guide and hold-down with zip ties. I don’t plan on pulling the wwm up or add other reinforcing other than micro-fibers to help w/ shrinkage cracks. I do plan on three saw cuts in each direction on the monolithic pour.
1) In Viega’s site as well as seeing the same thought elsewhere….. I see the installation recommendation about bridging construction (cold) joints and control (saw cut) joints. The Viega site recommends bridging and protecting the PEX tubing of any planned joint (both cold and saw cut joints) with 12” of rigid pvc tubing. So first question is has anyone ever experienced any problems with their tubing installation and use by NOT doing this at joints? I assume for the most part no one does this?
2) My current garage slab design has 7 loops of ½” PEX at 250’ length. I also intend to eventually incorporate future snow melting of a long sloped sidewalk and short concrete drive……I need to install the supply and return lines of these future 4 loops to the edge of the foundation wall and will eventually install the actual in slab PEX at a latter date. The PEX layout for snowmelt again has runs equaling 250’ length at foundation edge and I intend to use ½” PEX. I will run these four loop feeds under my garage slab to where I will eventually tie them into the snow melt and will insulate them for the approx. 50’ they will run under my slab (this makes the tubing runs 300' long). The snowmelt will be on its own zone for manual control. Second question – is there any benefit to insulating the snowmelt PEX as it runs under my garage slab? AND also is there any benefit to using a larger dia. PEX (5/8 or ¾) for this portion (I ask this because I mentioned the long sidewalk will slope…. about 20’ vertical over 125’ run).
Thanks for any and all input!
