This is a continuation of a previous thread. I am currently in a heated debate with my plumber about the proper venting of my toilet. This is a bathroom in a pole barn. Plumbing has been roughed in prior to concrete which is being poured later this week. Below are a few pictures. One is of how the plumbing is currently ran and the other is how I think it should be ran. Plumber states that the way the pipes currently are ran the toilet will vent from either of the sink lines once they are vented. I believe there needs to be a wye added to the 3" line right before the toilet but before where the shower line tee's in to act as a vent for the toilet. Who is right? I am withholding payment until I know this is done correctly.