New developemnt, about to pour concrete. 5" slab on 2in foam. 1/2 o2 pex. Rebar 12 center one way and 18 center other.
* Just to pour (i prep) labor quote is about $2-2500. Seems high? No pumper. 30x40 1200sq ft
* I keep hearing wite mesh is stronger! From four contractors.
* Was told to drill into my post which are sitting on a 24"x12" footer. And put rebar into them to tie the floor to the building?
* I have all the supplys and the bank said no more money for you, lol.
* I want a nice finish, i keep hearing burn it it real tight? Good or bad?
* Also sealing it, next day or 30 days later? Iv head both. Or not at all?
They said it will be like walking on ice.
Thanks