It seems, after looking through all the build threads I could, I've come to the conclusion that site prep is not an exact science. Either that, or it's so complicated that only the initiated few are privy to all the dark secrets that surround the subject and nothing short of a room full of robe clad strangers and a raw chicken offering will get me all the answers. So, I'll just ask some questions and hope no one throws me in the fire pit.
To frame this, the building will be used as an auto hobby shop.
From what I have gathered, the basic steps are thus...
1. Locate the site, taking surrounding slope and water drainage issues into account.
2. Removal of topsoil and all organic material going as deep as necessary. This material is soft and could result in unwanted settling or growth of plants or worse, trees where you don't want them. Save this material for later.
3. Bring in fill material (what kind is best?), bringing the level up to the highest point of the original undisturbed soil. Compacting between 3" layers.
4. Drill post holes and set the bottom skirt board a few inches (3?) off the ground (grade?).
5. Build the rest of the structure using the bottom of the skirt board as the start point.
6. Bring in fill material to build up the base, approximately 6 inches. If the skirt is a 2x10 and 3 inches above grade, 6 inches of fill puts the bottom of the concrete 6.5 inches below the top of the skirt which puts a 4" slab around 2.5 inches from the top of the skirt board.
7. Use the original topsoil to build of the perimeter to help drain water away from the building.
If this is at all right, and I need say 12' of clearance between concrete and ceiling, I need to make sure the ceiling is placed with respect to where i believe the top of the concrete will be, correct? So that would mean that as long as i cut my poles such that the tops are 13 feet from the bottom of the 2x10, I would have roughly 12.4' of clearance when everything is said and done.
So, do I have that close to correct? (or even close?)
As always, any and all responses are appreciated.

To frame this, the building will be used as an auto hobby shop.
From what I have gathered, the basic steps are thus...
1. Locate the site, taking surrounding slope and water drainage issues into account.
2. Removal of topsoil and all organic material going as deep as necessary. This material is soft and could result in unwanted settling or growth of plants or worse, trees where you don't want them. Save this material for later.
3. Bring in fill material (what kind is best?), bringing the level up to the highest point of the original undisturbed soil. Compacting between 3" layers.
4. Drill post holes and set the bottom skirt board a few inches (3?) off the ground (grade?).
5. Build the rest of the structure using the bottom of the skirt board as the start point.
6. Bring in fill material to build up the base, approximately 6 inches. If the skirt is a 2x10 and 3 inches above grade, 6 inches of fill puts the bottom of the concrete 6.5 inches below the top of the skirt which puts a 4" slab around 2.5 inches from the top of the skirt board.
7. Use the original topsoil to build of the perimeter to help drain water away from the building.
If this is at all right, and I need say 12' of clearance between concrete and ceiling, I need to make sure the ceiling is placed with respect to where i believe the top of the concrete will be, correct? So that would mean that as long as i cut my poles such that the tops are 13 feet from the bottom of the 2x10, I would have roughly 12.4' of clearance when everything is said and done.
So, do I have that close to correct? (or even close?)
As always, any and all responses are appreciated.
Last edited:


