Jimmyspeach
Member
Hello all I'm new to the Forum and have a question with regards to pouring over an existing slab
my garage was built in the 1940s and is 16 by 20 with a small apron that is approximately 8 feet by 6 feet
The slab and apron are in very good condition with no cracking the only problem is currently they sit approximately 6 in below grade therefore any rainfall or in the spring when the snow melts it absolutely floods the garage
Currently there is a solid inch of mud covering the slab and apron
my plan is to demolish the existing garage which I'm sure you can imagine the sill plates are 100% rotted from sitting in water for many years
The new garage slab would be 30 by 30
The new slab with completely incapsulate the old slab and apron
I'm in Wisconsin and would like to have the floor heated so I will be running PEX
Option a
I would have 2 inches of gravel on top of the old slab and then I would top that with 2 in of foam insulation and finally on top of that I would pour 4in of concrete
This would bring me an inch or 2 above grade I've talked to a couple of concrete guys that said the only way to do this is to remove the existing slab
Option B
If we remove the existing slab
The formula with change
3 inches of stone and or fill dirt then on top of that 3 in of gravel next the insulation and finally four inches of concrete
Not sure on this what do you guys think I'm really leaning towards option A just pouring over the existing slab
my garage was built in the 1940s and is 16 by 20 with a small apron that is approximately 8 feet by 6 feet
The slab and apron are in very good condition with no cracking the only problem is currently they sit approximately 6 in below grade therefore any rainfall or in the spring when the snow melts it absolutely floods the garage
Currently there is a solid inch of mud covering the slab and apron
my plan is to demolish the existing garage which I'm sure you can imagine the sill plates are 100% rotted from sitting in water for many years
The new garage slab would be 30 by 30
The new slab with completely incapsulate the old slab and apron
I'm in Wisconsin and would like to have the floor heated so I will be running PEX
Option a
I would have 2 inches of gravel on top of the old slab and then I would top that with 2 in of foam insulation and finally on top of that I would pour 4in of concrete
This would bring me an inch or 2 above grade I've talked to a couple of concrete guys that said the only way to do this is to remove the existing slab
Option B
If we remove the existing slab
The formula with change
3 inches of stone and or fill dirt then on top of that 3 in of gravel next the insulation and finally four inches of concrete
Not sure on this what do you guys think I'm really leaning towards option A just pouring over the existing slab
