Jimmyspeach
Member
Well I just need a place to vent people
So I poured my slab today i would give myself a D-
Ok my total slab is 22x30 at 4 inches thick is like 7.6 or so yards the 22x30 is actually a bit heavy as I'm counting the stem walls in that calculation
Being its myself a former buddy and just a day laborer my plan was to pour the back half of it this weekend and do the other half next weekend
So basically 2 separate pours at 4 yards each with a cold joint between them tied in by rebar
I basically divided the floor in 4 quarters
2 quarters today and the final 2 next weekend
I had my screed support pitched a 1.5 percent toward the garage door again I wish I had pictures to show how I had it set up so keep in mind i was going from back of the garage forward the garage is 30 feet deep stopping at the half way point approximately 14 feet off the back wall
That was the plan for today
Well here we go
The 1st quarter went smooth as butter
As we were finishing up the 1st quarter the driver said
Are you pouring that other half today
Yes I replied
Well you didnt order enough because there is less than a yard left on the truck you might have enough to do another 4 feet or so but then I'm out
And to get another yard delivered on a Saturday it's gonna be $500
So if I were you I would just keep pouring this little bit so you dont have to order more
What the driver was saying was keep working toward the front of the garage instead of doing the 2nd quater in the back of the garage
Well to add to it I have my buddy saying yea pour this last little bit because i gotta go
You knew i was pouring today for over a week and you were nice enough to show up 5 minutes before the truck and now 39 minutes later you gotta go yea ok
So is stupidly listened to the driver and said ok just empty it out
Well u know math dosent lie
Problem is we kept running towards the front were my screed board stopped at 14 feet as a result I quickly threw up a screed board and forgot to pitch it
As a result approximately 10 feet of my slab has a negative pitch I did quickly remember as I got close to the door so the final 8 feet has a very nice pitch when it gets to the door
My frustration is I spent hours setting my plan for this garage pour I'm kicking my self because I listened to the driver who was completely wrong
Time is critical when the truck shows up and I succumbed to the pressure of allowing outside influences to alter my plan
I was so frustrated when I saw my calculation was spot on
I mean there was less than a wheel Barrow of mud left
I just yielded to the driver figuring he was a professional so he must know what he is talking about
Lesson learned
MATH DONT LIE trust your research and instincts
Find a buddy that wont cut u short for his latest fling
Thank the driver but trust your calculation
I'm probably gonna tear out the 10 foot section and replace it
Im So frustrated
Thanks for reading I just needed to vent
So I poured my slab today i would give myself a D-
Ok my total slab is 22x30 at 4 inches thick is like 7.6 or so yards the 22x30 is actually a bit heavy as I'm counting the stem walls in that calculation
Being its myself a former buddy and just a day laborer my plan was to pour the back half of it this weekend and do the other half next weekend
So basically 2 separate pours at 4 yards each with a cold joint between them tied in by rebar
I basically divided the floor in 4 quarters
2 quarters today and the final 2 next weekend
I had my screed support pitched a 1.5 percent toward the garage door again I wish I had pictures to show how I had it set up so keep in mind i was going from back of the garage forward the garage is 30 feet deep stopping at the half way point approximately 14 feet off the back wall
That was the plan for today
Well here we go
The 1st quarter went smooth as butter
As we were finishing up the 1st quarter the driver said
Are you pouring that other half today
Yes I replied
Well you didnt order enough because there is less than a yard left on the truck you might have enough to do another 4 feet or so but then I'm out
And to get another yard delivered on a Saturday it's gonna be $500
So if I were you I would just keep pouring this little bit so you dont have to order more
What the driver was saying was keep working toward the front of the garage instead of doing the 2nd quater in the back of the garage
Well to add to it I have my buddy saying yea pour this last little bit because i gotta go
You knew i was pouring today for over a week and you were nice enough to show up 5 minutes before the truck and now 39 minutes later you gotta go yea ok
So is stupidly listened to the driver and said ok just empty it out
Well u know math dosent lie
Problem is we kept running towards the front were my screed board stopped at 14 feet as a result I quickly threw up a screed board and forgot to pitch it
As a result approximately 10 feet of my slab has a negative pitch I did quickly remember as I got close to the door so the final 8 feet has a very nice pitch when it gets to the door
My frustration is I spent hours setting my plan for this garage pour I'm kicking my self because I listened to the driver who was completely wrong
Time is critical when the truck shows up and I succumbed to the pressure of allowing outside influences to alter my plan
I was so frustrated when I saw my calculation was spot on
I mean there was less than a wheel Barrow of mud left
I just yielded to the driver figuring he was a professional so he must know what he is talking about
Lesson learned
MATH DONT LIE trust your research and instincts
Find a buddy that wont cut u short for his latest fling
Thank the driver but trust your calculation
I'm probably gonna tear out the 10 foot section and replace it
Im So frustrated
Thanks for reading I just needed to vent
