Just breaking ground on a new 30x60 detached shop/garage (metal building). It will be used primarily as a personal workshop, but will also have a large mancave/guest suite in it for extended stays with guests.
I'm trying to determine what size panel I need. The main power pole to our property is on the street exactly 1/2 way between the house and where the shop will be, so my initial thought was to have a new 200A service and meter run to the shop, to make sure I have plenty of power.
However, the cost of installation of all of that is more than triple the cost of having 100A service run to the shop from the house.
Here is a list of major loads:
240v 6O gallon, 3.2HP Compressor
Central A/C or mini split system
4 large ceiling fans (continuously running when occupied)
240V welder
All shop lighting will be LED
Small water heater (probably 40 gallon 5500W)
4 post lift (240V motor)
Small Electric Range in the mancave/apt
Typical TV, etc.. small loads
Evacuation Fan for welding/painting
So, I guess my question is: Will having just 100A service ever be an issue? I'm willing to spend the extra if it's going to be in question, but don't want to if it's not going to be an issue.
There will be times when the welder, compressor, and A/C systems will be all running at the same time, but I doubt it will be often.
Thanks!
Brian
I'm trying to determine what size panel I need. The main power pole to our property is on the street exactly 1/2 way between the house and where the shop will be, so my initial thought was to have a new 200A service and meter run to the shop, to make sure I have plenty of power.
However, the cost of installation of all of that is more than triple the cost of having 100A service run to the shop from the house.
Here is a list of major loads:
240v 6O gallon, 3.2HP Compressor
Central A/C or mini split system
4 large ceiling fans (continuously running when occupied)
240V welder
All shop lighting will be LED
Small water heater (probably 40 gallon 5500W)
4 post lift (240V motor)
Small Electric Range in the mancave/apt
Typical TV, etc.. small loads
Evacuation Fan for welding/painting
So, I guess my question is: Will having just 100A service ever be an issue? I'm willing to spend the extra if it's going to be in question, but don't want to if it's not going to be an issue.
There will be times when the welder, compressor, and A/C systems will be all running at the same time, but I doubt it will be often.
Thanks!
Brian
Last edited: