Pressure Treated or Not?

robertwhite

Well-known member
Joined
Feb 10, 2010
Messages
433
Need to replace a couple of floor joists in a 60 yr old kitchen. Original joists are oak that is now hard as a rock. Unfortunately, a couple are cracked and I'm not comfortable leaving them.

Joists are 18" above dirt floor (floor has no vapor barrier) and there is tar paper anywhere the joists sit on. Now obviously, by code (even though we don't have codes here), PT is not required. I am however more comfortable with having a PT vs regular lumber just for the dampness factor.

Here's the issue........... If I use PT, when it dries out and shrinks, won't it take my floor with it and pull the floor down?

So do I use regular interior lumber that won't shrink or use PT and take my chances on it pulling the floor down in that one section?
 
To avoid these ads, REGISTER NOW!

Milton Shaw

Well-known member
Joined
Feb 11, 2011
Messages
4,868
PT will warp and curl as it dries out. I would use Number 2 construction grade and then if you can put some metal shields on the ends to protect from moisture/bugs.
 

dutchgray

Well-known member
Joined
Sep 28, 2014
Messages
6,485
Location
Dorset. England.
Or set them a touch high so when they shrink it ends up level, if you cant wait to do the job. Or just sister on to the cracked ones so it don't matter when they shrink.
 

CNGsaves

Well-known member
Joined
Sep 26, 2012
Messages
13,233
Location
KS and OK
So . . . . RobertWhite . . . . are you . . WalterWhite's brother ?? . . . from BB ??

You out in desert of New Mexico ??? :D

;) . . ;) . . . seriously, WHERE is here ??

Update GJ Profile with City/State/Country.

You'll get best advice when supplied with more information.
 
OP
R

robertwhite

Well-known member
Joined
Feb 10, 2010
Messages
433
Buy pressure treated and wait 30 days for it to shrink and dry out before installing it?

Can't wait, has to be done now.


Or just sister on to the cracked ones so it don't matter when they shrink.

That is what I was thinking, and probably what I will do. The old joist is not rotted, it's just got a long (2ft) crack in the middle, so sistering should work.
 

Kevin54

MEMBER EMERITUS
Joined
Jan 12, 2005
Messages
29,341
Location
Urbana, Ohio
Buy pressure treated and wait 30 days for it to shrink and dry out before installing it?

The only bad thing about laying it out and waiting 30 days for it to dry out, it will be twisted and warped something terrible. I would get it, and fasten everything together the way it is when you get it. It will help eliminate some of the twisting and bowing.

I have a 6x6 post that I was going to use for a porch post, but it has twisted around probably 10-15 degrees from one end to the other, so it will get used as a fence post where I can hide most of the twist. And this post has twisted even though it has (6) 80 lb. bags of concrete sitting on it.

Are you replacing the current joist, or are you going to sister joist beside the ones you need to replace?
 

Leaflessshadetree

Well-known member
Joined
Aug 1, 2013
Messages
7,211
Location
Don't ask.
Use regular construction grade lumber but waterproof it with your choice of sealants.
Pressure treated wood will eat most nails and fasteners.
 
To avoid these ads, REGISTER NOW!

WVBrady

Well-known member
Joined
May 5, 2005
Messages
1,679
Location
WV
Can't wait, has to be done now.




That is what I was thinking, and probably what I will do. The old joist is not rotted, it's just got a long (2ft) crack in the middle, so sistering should work.
I would sister it with the best waterproof glue you can get and draw them together with screws, then use nails for increased shear strength.
 

curliejones

Active member
Joined
Aug 19, 2013
Messages
34
Pick through the stack and get straight grained boards that are cut straight to begin with. Sight down the board and/or place them on a level floor on edge to see if it's straight. Lay it on the flat side when you get home supported at least every 3 ft and place a few concrete blocks on top. Keep out of the sun to avoid drying one side much faster than the other, but make sure the location has good air flow. Move blocks and support every 4 days. Alternatively: try to find KDAT - I understand that kiln dried after treatment is available but I don't know where around here.
 

Catadj78

Well-known member
Joined
Aug 11, 2014
Messages
1,009
Location
Alabama
Sister it with pt. Use hot dipped galvanized nails.

Nail it up when you get it, it will be fine
 

captaindiode

Well-known member
Joined
Jul 8, 2013
Messages
373
Location
NC
You can buy KDAT (kiln dried after treatment) pressure treated. You may have to hunt for it at a real lumber yard instead of a big box. Yellawood is one name brand. Also, if you use PT, remember that all fastners that enter the lumber must be hot dipped galvanized, ceramic coated, or stainless. The copper content will corrode anything else in short time.
 

Cyberbear

Well-known member
Joined
Nov 23, 2013
Messages
1,524
Location
California
You don't mention the span of the existing oak floor joists, or the size of the present in place joists. Based on the small amount of information, I could suggest the previously mentioned sistering is a good idea. You may have the option of doing both sides, if necessary, as well as putting a couple of ready made concrete piers set on 12" concrete stepping pavers to support the existing floor joists that are 18" above grade. This should more than correct any existing and future settling problems. They also sell economical foundation screw jacks that you can adjust, as needed, over time for another type of quick fix.
 