gtae07
Well-known member
Hopefully this weekend I'll be trenching and laying conduit for my power feed from the house (90A subpanel in shop, 2-2-2-4 MHF). I'm looking at right about 100ft of 2" conduit, with two 90deg sweeps plus a gradual 10-15 deg bend over the length. I get that, because the glue can eat the cable's insulation, I have to lay the conduit and pull the cable afterwards; the question is, how do I do that? Yes, use lots of lube and have one guy feeding while the other pulls, but how do I attach to the cable, what do I pull it with, and how much force should I expect it to take?