Most buildings I see use a "bolt up" main beam structure. 2 posts and a 2 piece beam spanning the center of the build. I rarely see these main beams welded up. Is there a reason other than its easier to weld flanges in the shop and bolt it up on the job site ?
 
To avoid these ads, REGISTER NOW!

kwb

Well-known member
Joined
May 1, 2009
Messages
1,782
Location
PNW
Field welds are expensive compared to a small box of bolts. Typically in the trades for commercial work - Welders weld and that is about it. They command a pretty good premium so it makes sense to not have them around a lot or have them doing tasks that don't bill out at that rate. A lot of the time it is also necessary to have a 3rd party CWI inspect to get buy-off on permitted work.

Even with really bad torque control, the engineer can make a prediction that it will meet minimum standards. Most anyone can read the markings on the heads of the bolts to verify they meet spec.
 

MBfreak

MEMBER EMERITUS
Joined
Dec 10, 2010
Messages
2,301
Location
Linkoping , Sweden
Welding in a building with lots of wood structures and maybe also less than perfect housekeeping is a fire hazard. Welding spats creep everywhere and onset that is visible may be several hours later.

Ola
 

readhead

Well-known member
Joined
Dec 8, 2012
Messages
6,198
Location
Durango, Co.
As an erector it is much easier and faster to bolt up than weld. Spending some shop time at the front saves a lot of labor at the back.
 
To avoid these ads, REGISTER NOW!

cvairwerks

Well-known member
Joined
Aug 12, 2016
Messages
7,304
Location
Within hearing distance of Texas Motor Speedway
We did a couple weldup main beams when I did steel building work. Took a lot more time and equipment to get them finished and up into place. Get past a certain length and now you need bigger cranes and spreader bars to handle the weight and twist. The last one I worked, required a pair of 75 ton crawler cranes to lift into place and we were on hold for 3 days due to wind issues. Couldn't do the lift if winds were over 5 mph, due to the reach required and the crane positioning. Had it been a boltup beam, we wouldn't have had to worry and could have had one smaller crane hold the center joint as we lifted the halves with our forklift.
 

dcg9381

Well-known member
Joined
Jun 20, 2018
Messages
12,003
Location
Austin, TX
Here, it's 20-30% more expensive to assemble a "bolt up" building. Why? Precision is required. The welders can weld a lot faster than you can bolt things together. Weld up they just weld up and trim...

Advantage of a bolt-up seems to be that it can be considered an "engineered structure" and a stamp provided from the building supplier (Mueller).
 

readhead

Well-known member
Joined
Dec 8, 2012
Messages
6,198
Location
Durango, Co.
Your missing the part of a weld up building where the time is spent detailing, layout and cutting the parts. A bolted connection will go together faster than a welder can weld on a similar sized joint.
I think I can say that with confidence after forty plus years as a welder and erector.
 