keeps raining on my parade...lol, I dug out the hillside(highlift) to build my garage friday,32x64x14 they are susposto pour the footers(form-a-drain) wednesday May 13, then stem walls and the floor the folowing days, but with all this rain the last two days i just don't see it drying out enough to get a truck with forms and concrete up in there to pour wednesday, driveway is a uphill grade and like pudding, I did dig small ditches all day to direct all the water away from where the footers will go so it isn't standing water like it was this morning....just a little aggrivated, ok well alot, I have been working so hard pulling strings GC'ing this thing myself and begging subs to come out and do the work at stages, and I finnaly get on a schedule and now this, wish me luck on the reschedule, and digging out colapsed walls 8 ft at the back corner....lol well it wasn't earlier before it got dark and started pouring again. rant over..lol