I have a combination of rebar & wire mesh laid out in a slab ready to pour (probably wednesday). This is all on a plastic vapor barrier. The rebar was sort of an afterthought on the part of the builder, but was left over from the helluva wall we built for the back wall of the garage. Right now the rebar (>10' pieces) is in a grid, perhaps at 2.5' centers, but we didn't have enough to cover all of the floor. It's focused on the main entrances to the garage bays, but I have only the mesh farther back. (36' wide, 30' deep). Is there enough greater value strength-wise with rebar for the floor to be worth using the same grid throughout the garage? The area where my 2 post lift is likely to be located is covered & I expect a 4 post lift to be somewhere (maybe multiple locations) in the garage, but probably no other really substantial point loads.