Recommendation/ Course of Action

DTL504

Well-known member
Joined
Jan 9, 2011
Messages
62
Location
Sandhills, North Carolina
In hindsight, I should have run all my Romex close to the eaves as possible during rough-in of electrical. Now I want to use all the space in my 30' X 42' garage and extend the 16' X 42' loft by maximizing space behind the knee wall for additional storage. The left knee wall was not an issue, I added subfloor to gain storage space. However, the right-side knee wall has Romex running over joist to the main panel. This has left me with three possible Courses of Action:

1. Notch the joist with a router to store the wire, cover with metal strap then add subfloor.

2. Raise the floor by sistering 2 x 10 to the joist then add sub-floor.

3. Reroute all the electrical wire into junction boxes. (Least preferred option)

4. Do nothing, enjoy the space you have.
 

Attachments

  • Left wall.jpg
    Left wall.jpg
    104.9 KB · Views: 37
  • Romex Wire.jpg
    Romex Wire.jpg
    102.7 KB · Views: 36
  • 20230527_211935.jpg
    20230527_211935.jpg
    490.2 KB · Views: 37
  • 20230527_211900.jpg
    20230527_211900.jpg
    252.4 KB · Views: 36
To avoid these ads, REGISTER NOW!
To avoid these ads, REGISTER NOW!
Top Bottom