My home’s prior owner relocated one of the basement columns by about 48”. I assume this was to accommodate a door in a framed room. They simply cut off the column at the floor, tack welded a plate to the bottom and used a piece of 2x4 and shims between it and the floor to snug it into the new location. Not that it seems to be a problem, the relocated column left just over 12’ of main beam unsupported. Whereas the relocated column is again nailed to the underside of the main beam, the bottom is not secured to the floor. A good kick would dislodge it. They filled the cut off pipe in the floor at the original location with concrete.
For reference, the basement columns are 4” diameter steel and are embedded in the concrete floor, at about 104” on center. There is a plate welded to the column top that is attached to the underside of the main beam (3 - 2x10’s laminated together) with nails. It’s about 75.5” from the concrete floor to the underside of the main beam.
Due to the basement flooding in 2001, I gutted the basement of all framed walls. (FWIW, all basement flooding problems have been resolved).
To accommodate some basement storage projects, I’d like to relocate this column back to the original location. Whereas I could buy a new jack column, there are none available locally that are short enough, and even if available, they cost more than double of one of these: https://www.lowes.com/pd/Akron-14-in-Adjustable-Jack-Post/1000054567
My plan is to weld it to the bottom of the existing column, then after installation, anchor it both to the floor and overhead beam. Before moving the relocated column, I’ll shore up the main beam using 2x4s . I also plan on using a laser level and story stick to confirm the main beam elevation doesn’t change.
Any concerns or caveats I should consider in this plan?
For reference, the basement columns are 4” diameter steel and are embedded in the concrete floor, at about 104” on center. There is a plate welded to the column top that is attached to the underside of the main beam (3 - 2x10’s laminated together) with nails. It’s about 75.5” from the concrete floor to the underside of the main beam.
Due to the basement flooding in 2001, I gutted the basement of all framed walls. (FWIW, all basement flooding problems have been resolved).
To accommodate some basement storage projects, I’d like to relocate this column back to the original location. Whereas I could buy a new jack column, there are none available locally that are short enough, and even if available, they cost more than double of one of these: https://www.lowes.com/pd/Akron-14-in-Adjustable-Jack-Post/1000054567
My plan is to weld it to the bottom of the existing column, then after installation, anchor it both to the floor and overhead beam. Before moving the relocated column, I’ll shore up the main beam using 2x4s . I also plan on using a laser level and story stick to confirm the main beam elevation doesn’t change.
Any concerns or caveats I should consider in this plan?
