Hello Folks.
Here is the deal. The service into the electrical panel is on the west end of the building. We need to relocate that panel about 200' for a remodel.
It is impossible to run a new service in at the other end of the building. So we have to work with it's current location.
One contractor wanted to remove that electrical panel. Put in a 200 amp disconnect. Then run new cable from that to the new location for the new electrical panel and then wire everything from that.
Contractor two. Wanted to replace the electrical panel at its current location. Then run everything out of that panel 200 feet to the new lights, outlets ect.
Option one seems easier to me. Just not sure if one is more or less correct.
Thanks,
Capt. Chrysler
Here is the deal. The service into the electrical panel is on the west end of the building. We need to relocate that panel about 200' for a remodel.
It is impossible to run a new service in at the other end of the building. So we have to work with it's current location.
One contractor wanted to remove that electrical panel. Put in a 200 amp disconnect. Then run new cable from that to the new location for the new electrical panel and then wire everything from that.
Contractor two. Wanted to replace the electrical panel at its current location. Then run everything out of that panel 200 feet to the new lights, outlets ect.
Option one seems easier to me. Just not sure if one is more or less correct.
Thanks,
Capt. Chrysler