so I'm going to be adding a small retaining wall to my back yard and bringing in some fill to take some grade out to give the kids a more usable yard. The wall will be about 70 feet long and range from about 8"to 24". My question is. Should i bring the fill in first spread and compact it. Then cut into the face of the newly compacted hill side and build the wall or build the wall first and then backfill to it. This is the way i built a previous smaller wall. But that wall was more astetic with the way the grade was their is very minimal loading of the other wall. I also felt like i used alot more stone. Any thoughts or opinions are appreciated