Rigid metal conduit underground

bluedog225

Well-known member
Joined
Jan 31, 2012
Messages
3,389
Location
Texas
I’ve been reading about using rigid metal conduit underground. I’ve got a run of about 40’. Looks like corrosion is a real issue. The alternative is schedule 80 pvc. Looks like the rigid can be buried at 6” while the PVC requires 18”. Ugh.

And the other alternative is direct burial cable. 24” but could be a pretty narrow trench.

I’m about to abandon my plan to use my nice 2” rigid conduit underground and go with schedule 80. I wanted to check in and make sure this was the right move for maximum service life. I’ll use the rigid somewhere else.
 
To avoid these ads, REGISTER NOW!

Mzungu

Well-known member
Joined
Sep 3, 2022
Messages
176
We stopped using rigid metal underground many years ago. Nowadays its Teck cable with special explosion proof glands and seals for gas stations. For all other "normal" UG conduit installs its rigid PVC schedule 40. 18" for non-vehicular traffic areas.
 

mike93lx

ALLIANCE MEMBER
Joined
Dec 9, 2013
Messages
38,398
Location
Richmond, VA
Underground rigid is for gas stations. I don't know why anyone would want to subject themselves to that kind of work otherwise.

Use PVC. You can use schedule 40 and save some money. Schedule 80 is for where damage could occur.

And a trencher doesn't know the difference between 6" and 18" of depth.
Agree except on the depth. You must not have rocks or clay in your soil.
 

sparky 1971

Well-known member
Joined
Oct 9, 2018
Messages
8,131
Location
Central Iowa
Agree except on the depth. You must not have rocks or clay in your soil.
Oh, there's nothing but clay around me and about 25 miles to the South it turns pretty rocky. The guy I use to trench has a Ditch Witch that will get about 6' of depth. If and when a rock is hit, he turns around and uses the attached back hoe to get it out. It's been 11 years since I trenched. I tell people someone else is doing the digging and that I have a guy, or they can take care of it themselves.
 

mike93lx

ALLIANCE MEMBER
Joined
Dec 9, 2013
Messages
38,398
Location
Richmond, VA
Oh, there's nothing but clay around me and about 25 miles to the South it turns pretty rocky. The guy I use to trench has a Ditch Witch that will get about 6' of depth. If and when a rock is hit, he turns around and uses the attached back hoe to get it out. It's been 11 years since I trenched. I tell people someone else is doing the digging and that I have a guy, or they can take care of it themselves.
Well, that's cheating. Homeowners rent machines that most certainly do care about the difference between 6" and 24". I have no rocks around me now, but it's hard clay and back in New England, the rocks were absolutely everywhere.

Sounds like that's a good guy to keep on your side
 

sparky 1971

Well-known member
Joined
Oct 9, 2018
Messages
8,131
Location
Central Iowa
Well, that's cheating. Homeowners rent machines that most certainly do care about the difference between 6" and 24". I have no rocks around me now, but it's hard clay and back in New England, the rocks were absolutely everywhere.

Sounds like that's a good guy to keep on your side
The last time I trenched I rented a walk behind trencher. I don't like to say never, but I hope to never, ever use one of those POS's again. If I have to I will get a mini excavator and tear the hell out of everything, but there's no way I'm using a trencher. That's where I give people to option of my guy or figuring it out themselves.
 

sparky 1971

Well-known member
Joined
Oct 9, 2018
Messages
8,131
Location
Central Iowa
My trencher is almost 60. He knows….😂
By using PVC instead of rigid, the saving will pay for at least part of a machine rental. I would look into a mini excavator. Walk behind trenchers are a PITA. Or you could hire someone that digs for a living and get it over with.
 

Chuckster in NJ

Well-known member
Joined
Jan 26, 2010
Messages
2,390
Location
Hunterdon County NJ
I had a Ditch Witch 1420 walk behind trencher and most of the time after a use in "tough soils" it had to be repaired……. The machine "earned it’s keep" over the years but it was a 4 hour maintenance job in my shop after 700 feet of trenching.
I purchased the trencher in 1984 and sold it in 1999, I had no problem selling the machine because it would fit through a 36” gate and was well maintained.
 

dogdog

Well-known member
Joined
Nov 15, 2011
Messages
12,711
dependents on what you are doing and what is important to you... GRC/RMC are better at preventing damages from some one digging into it...but more expensive... and is NPS threads I think. It is heavily galvanized or zinc coated to prevent rust... don't think the ones I bury from 2013 is rusting yet at all. PVC is cheaper, pretty sure you know the rest. I dig my trench down to 30"... it's not that hard to dig 40' . didn't even hire any home depot park lot rental special.
 

billconner

Well-known member
Joined
Jul 20, 2021
Messages
6,996
Location
Thousand Islands NYS
I have twice used rigid metal because of the shallow depth - one or two sticks of 1". I see 2" rigid is $108 a stick vs 2" PVC at $35. 1" $44 vs $15. Digging by hand for a 10 to 15' run, the rigid metal seemed worth it to me. Going 40 ft with 2" - $432 vs $140 in material - I'd never hand dig for 18" cover, might for 6".
 
To avoid these ads, REGISTER NOW!

Jim greengo

Well-known member
Joined
Sep 3, 2018
Messages
7,415
Location
Behind my house
Underground rigid is for gas stations. I don't know why anyone would want to subject themselves to that kind of work otherwise.

Use PVC. You can use schedule 40 and save some money. Schedule 80 is for where damage could occur.

And a trencher doesn't know the difference between 6" and 18" of depth.
I've used it underground in industrial settings,but it's been many years ago.
 

Jim greengo

Well-known member
Joined
Sep 3, 2018
Messages
7,415
Location
Behind my house
And I dont miss bending rigid conduit,ran more than I'd like to remember in ag processing plants in the 90s.
I'll take bending a mile of 1" emt over 100' of freaking rigid and threading that **** together/hanging it! Hahaha
 

sparky 1971

Well-known member
Joined
Oct 9, 2018
Messages
8,131
Location
Central Iowa
And I dont miss bending rigid conduit,ran more than I'd like to remember in ag processing plants in the 90s.
I'll take bending a mile of 1" emt over 100' of freaking rigid and threading that **** together/hanging it! Hahaha
I hate rigid. I have a 300 threader and dies up to 2", a Greenlee 1818 with shoes to 1-1/2 and a segment bender with shoes that are way bigger than I ever am going to deal with. If I never have to use any of those again I won't complain one bit. My idea of rigid these days is a mast that goes straight up.
 

beemerphile

Well-known member
Joined
Jul 9, 2021
Messages
727
Location
Danielsville, GA USA
Oh, there's nothing but clay around me and about 25 miles to the South it turns pretty rocky. The guy I use to trench has a Ditch Witch that will get about 6' of depth. If and when a rock is hit, he turns around and uses the attached back hoe to get it out. It's been 11 years since I trenched. I tell people someone else is doing the digging and that I have a guy, or they can take care of it themselves.
It's all about location. I had a guy digging what I thought was going to be a 24" direct burial trench for the feeder to my new house. The DW hit rock and every time one of the carbide teeth impacted the rock I could feel it under my feet 30 feet away because I was standing on the same rock he was banging on. Forget the backhoe. I finally carved out about 9 inches of cover but ended up running the feeder in metal conduit on the side of my shop to get past the mega rock.
 

Jim greengo

Well-known member
Joined
Sep 3, 2018
Messages
7,415
Location
Behind my house
I hate rigid. I have a 300 threader and dies up to 2", a Greenlee 1818 with shoes to 1-1/2 and a segment bender with shoes that are way bigger than I ever am going to deal with. If I never have to use any of those again I won't complain one bit. My idea of rigid these days is a mast that goes straight up.
Amen brother! Hahaha
 

walrus

Well-known member
Joined
Nov 12, 2008
Messages
11,697
Location
Maine
If you are going to wrap pipe might as well hook an anode on it also. Rigid will outlast the OP if his comment on ditch digger being 60 is true. What might stop him from using rigid is price
 

sparky 1971

Well-known member
Joined
Oct 9, 2018
Messages
8,131
Location
Central Iowa
You guys complaining about rigid...
That reminds me of the one and only big rigid job I ever worked, a grain elevator remodel. It was supposed to take a month, but drug on for five and I hated every minute of it. The largest conduit we used was 2" but during January and February it was so cold that in between threads we had to put the oil in a shed with a heat lamp shining on it. Otherwise the oil wouldn't pump. Never again.
 

Jim greengo

Well-known member
Joined
Sep 3, 2018
Messages
7,415
Location
Behind my house
That reminds me of the one and only big rigid job I ever worked, a grain elevator remodel. It was supposed to take a month, but drug on for five and I hated every minute of it. The largest conduit we used was 2" but during January and February it was so cold that in between threads we had to put the oil in a shed with a heat lamp shining on it. Otherwise the oil wouldn't pump. Never again.
We did a soybean oil processing plant in south dakota in mid 90s.
Ran miles of rigid pipe on that job,lots of 3" and 4" stuff between buildings.
Used to wire lots of packing plants back in the day also,anything that was anywhere near live cattle was rigid.
We ran emt for most stuff on the fab side and freezers though.
That's a much younger man's sport to say the least,I'd rather flip hamburgers at mcdonalds than do that stuff anymore!
 

Norcal

Well-known member
Joined
Mar 16, 2008
Messages
13,792
It seems that the worst corrosion w/ metal underground pipe is where it emerges from the ground, so I just use pipe wrap tape there.
 

Bert_

Well-known member
Joined
Dec 24, 2016
Messages
9,881
Location
NW Iowa
That reminds me of the one and only big rigid job I ever worked, a grain elevator remodel. It was supposed to take a month, but drug on for five and I hated every minute of it. The largest conduit we used was 2" but during January and February it was so cold that in between threads we had to put the oil in a shed with a heat lamp shining on it. Otherwise the oil wouldn't pump. Never again.
I actually said no to this job the first time. But they came back a couple days later and asked again so I could pretty much set my own terms. We had snow but the temp was probably 25* so not bad really. Ran a 600A feeder to a dryer. Just a few day job. Snow is all melted now.
 