Angelfire
Well-known member
Hiya Folks,
My buildout of the garage involves me reusing some of the wiring already installed. Shouldn't be an issue. However, I have a switch box that is currently installed and I will need to make up new circuits in it. The existing switches in the box control the lighting that is currently installed. When I'm done installing my stuff, I will have a 2-3 new runs feeding into this box/switches and will have removed one or two runs that are existing. How do I present this for rough in? I really can't lose the lights until I'm ready for drywall (which will be a while) so was thinking I'd just run the cables over and leave them outside the box until I'm ready for drywall (at which time, I'd be taking the lights down anyway to get rock up on the ceiling). Is this acceptable to most inspectors? An alternative would be to just temporarily hang lights where I plan them to be after drywall and hook everything up. This assumes the inspector will allow for power turn on after rough in inspection. I know how all this works at my place of business with regards to power on etc...but am not sure in the residential world as to when I can turn power on during the permit process. I hope I explained this ok.
Thanks for any insight.
Cheers.
My buildout of the garage involves me reusing some of the wiring already installed. Shouldn't be an issue. However, I have a switch box that is currently installed and I will need to make up new circuits in it. The existing switches in the box control the lighting that is currently installed. When I'm done installing my stuff, I will have a 2-3 new runs feeding into this box/switches and will have removed one or two runs that are existing. How do I present this for rough in? I really can't lose the lights until I'm ready for drywall (which will be a while) so was thinking I'd just run the cables over and leave them outside the box until I'm ready for drywall (at which time, I'd be taking the lights down anyway to get rock up on the ceiling). Is this acceptable to most inspectors? An alternative would be to just temporarily hang lights where I plan them to be after drywall and hook everything up. This assumes the inspector will allow for power turn on after rough in inspection. I know how all this works at my place of business with regards to power on etc...but am not sure in the residential world as to when I can turn power on during the permit process. I hope I explained this ok.
Thanks for any insight.
Cheers.