Getting ready to trench and finalize electrical and looking for input from anyone who’s tackled a similar setup.
Setup:
Electrical Load (Calculated):
Utility: Florida Power & Light (FPL)
Engineered plans are complete and ready to submit — the only open question is which electrical path to go with.
Option 1: Upgrade to 400A at the house
Looking for feedback on:
Appreciate any advice before we commit and start buying materials.
Setup:
- 1989-built home with a full 200A panel (original 42-slot, aluminum wiring)
- Detached Large Garage is 140’ from the house
- Detached Small Garage is another 130’ beyond that
- This is an owner-builder project
Electrical Load (Calculated):
- Large Garage: ~150A peak
- Small Garage: ~70A peak
Utility: Florida Power & Light (FPL)
- FPL has already approved our request for a second meter
- The senior engineer has been very helpful in prepping us for this option
- Second meter run would be ~200’ from the existing transformer
Engineered plans are complete and ready to submit — the only open question is which electrical path to go with.
Option 1: Upgrade to 400A at the house
- Replace existing panel with 400A service
- Run 300 kcmil AL to a 200A subpanel in the Large Garage
- Run 1/0 AL from there to a 100A subpanel in the Small Garage
- New 200A service drop to the Large Garage
- Feed the Small Garage from there with 1/0 AL to a 100A subpanel
Looking for feedback on:
- Long-term pros/cons of dual services vs. a single upgraded service
- Utility base fees or inspection experiences with dual meters
- Generator / backup power integration challenges
- Anything you’d do differently if you were in our shoes
Appreciate any advice before we commit and start buying materials.