To avoid these ads, REGISTER NOW!

Self leveling mortar?

imagineer

Well-known member
Joined
Dec 13, 2015
Messages
1,018
Location
Ohio
Question for those with concrete floor experience…

I want to improve the floor in Mrs. Imagineer’s greenhouse. Currently, the floor is 4”x8”x2” thick brick pavers, dry-set on a ~1” bed of ‘sand’. Actually, I was too cheap to purchase masonry sand and used spent waterjet garnet instead. (Where I work, we generate about 2 tons of spent garnet each day.)

Whereas I did an ok job of leveling out the garnet before putting down the pavers, the floor is not ‘pool table level’. Also, ants and all matter of bugs are living their best lives in the garnet.

Late this summer when the greenhouse will be empty, I want to take up all the pavers and remove the garnet. Then pour in some sort of self-leveling concrete or mortar. I’ll add mesh or rebar for strength if needed. After it’s dry, I’ll reset the pavers.

My questions:

Does a bagged masonry product for a project this size (11’ x 12’) like this exist?

Expecting the project will need about 1 – 1.5 yards, can it be mixed & poured fast enough that it can fill the frame and settle before it sets? I figured I’d rent a cement mixer for the project.

Would it be better to do this in 4 pours, leveling the 2nd, 3rd and 4th pours to the 1st?
 
To avoid these ads, REGISTER NOW!

DavidR8

Well-known member
Joined
Aug 27, 2019
Messages
269
Location
Victoria, BC
I'd just use regular concrete. With care and attention paid to leveling the forms and screeding it should be plenty good for a greenhouse.
 
OP
I

imagineer

Well-known member
Joined
Dec 13, 2015
Messages
1,018
Location
Ohio
Regular concrete . . . I'm hoping to not have to make level forms to pour into. The greenhouse sits on 2x12s on edge with the tops of the pavers about 7" down from the top of the 2x12s. There won't be much opportunity to screed. The actual finished height of the floor is arbitrary.

Just pour a slab? . . . I avoided having a property tax re-evaluation by not using a concrete slab (any structure, on concrete with utilities, requires getting a building permit; which would have triggered the county auditor). The greenhouse is considered "temporary" and is designed to be unassembled and moved if needed.
 

mike93lx

ALLIANCE MEMBER
Joined
Dec 9, 2013
Messages
37,847
Location
Richmond, VA
Regular concrete . . . I'm hoping to not have to make level forms to pour into. The greenhouse sits on 2x12s on edge with the tops of the pavers about 7" down from the top of the 2x12s. There won't be much opportunity to screed. The actual finished height of the floor is arbitrary.

Just pour a slab? . . . I avoided having a property tax re-evaluation by not using a concrete slab (any structure, on concrete with utilities, requires getting a building permit; which would have triggered the county auditor). The greenhouse is considered "temporary" and is designed to be unassembled and moved if needed.
They'll never know
 
OP
I

imagineer

Well-known member
Joined
Dec 13, 2015
Messages
1,018
Location
Ohio
What if the slab is inside and not supporting the structure?
That would skirt the issue of the permit, but being inside a frame with access though a man-door, I doubt I'd be able to screed it level without making a mess of it.

Besides, Mrs. Imagineer and I are 5 years or so from retirement and if we end up moving, the greenhouse will come with. I'm thinking it will be easier to break up and discard a weaker 2" thick layer of self-leveling than a full slab.
 

mike93lx

ALLIANCE MEMBER
Joined
Dec 9, 2013
Messages
37,847
Location
Richmond, VA
That would skirt the issue of the permit, but being inside a frame with access though a man-door, I doubt I'd be able to screed it level without making a mess of it.

Besides, Mrs. Imagineer and I are 5 years or so from retirement and if we end up moving, the greenhouse will come with. I'm thinking it will be easier to break up and discard a weaker 2" thick layer of self-leveling than a full slab.
Screeding as you move back to the door is a normal thing, but if you really don't want to do a slab, I wouldn't pour self leveler for this at all. You can easily get it flat with normal, compacted base. If you don't compact anyway, the leveler will crack. It's the wrong stuff for the application
 
To avoid these ads, REGISTER NOW!

duneslider

Well-known member
Joined
Jan 20, 2013
Messages
2,267
Location
Riverton, Utah
This is not the right application for self leveler and it would end up costing a fortune compared to concrete. Just pour the concrete 2" thick, it will come out just as easy as 2" of self leveler would
 

Hilltopmasonry

Well-known member
Joined
Oct 12, 2015
Messages
2,170
Self leveling concrete/grout/mortar is crazy expensive

I would just use concrete and make it a little wet
 
OP
I

imagineer

Well-known member
Joined
Dec 13, 2015
Messages
1,018
Location
Ohio
Self leveling concrete/grout/mortar is crazy expensive

I would just use concrete and make it a little wet
This is probably the direction I'll go, and add an extra mesh panel.

Still, the problem will be time. There's no way to back a cement truck to the the site, so I'll be pulling this off using a portable mixer and bags of concrete. As it's configured now, it's 11' x 12', which will take about 70 - 80lb bags. I need to figure out how to mix and pour all the material and still have time to try and level it before it sets up. Fortunately, I've got til September to figure it out.
 

f121

Well-known member
Joined
Dec 8, 2018
Messages
2,080
Location
UK
I’d just bang a self leveling screed down. You have to trowel it somewhere near flat and then gravity does the rest. Pretty easy job.
 

rancherbill

Well-known member
Joined
Oct 18, 2007
Messages
5,335
Location
Foothills County, Alberta, Canada
I want to improve the floor in Mrs. Imagineer’s greenhouse. Currently, the floor is 4”x8”x2” thick brick pavers, dry-set on a ~1” bed of ‘sand’. Actually, I was too cheap to purchase masonry sand and used spent waterjet garnet instead. (Where I work, we generate about 2 tons of spent garnet each day.)

Whereas I did an ok job of leveling out the garnet before putting down the pavers, the floor is not ‘pool table level’. Also, ants and all matter of bugs are living their best lives in the garnet.
Leave it alone. Buy an ant trap (or whatever) to get rid of the critters. You want / need drainage. There is lots of water in green houses and you'll end up with mold and mildew.

My green house has washed sand (mortar) and re-used patio bricks. The ants thought they were in heaven until I put some ant traps in the greenhouse. I conpacted the sand with a simple 8' 4x4 held vertically used as a tamper. Lift the post about a foot and let it fall down. It slams with a lot of force and then I simply smoothed with a 4' board. It has stayed very flat. and smooth.
 

duneslider

Well-known member
Joined
Jan 20, 2013
Messages
2,267
Location
Riverton, Utah
Find someone that rents one of these MudMixers in your area. MudMIxer They work amazingly well and will make quick work of your job, especially if there are two of you, take turns loading the bags and spreading things around.
 

Kaizen

Well-known member
Joined
Jan 9, 2015
Messages
6,948
Location
New England
level pavers and use polymeric sand in the joints. you'll be done in a few hours and only need a few bags. usually available locally in a few different places
 

zendriver

Well-known member
Joined
Dec 10, 2014
Messages
30,122
Location
Indiana
Cubic Yard and a half, He's not going to see you bring in 70 bags of something? :headscrat

IMO, put a level chalk line on each side of the wood where you want the top of the floor. Put the first mix 8" strip out from the wood, level along the chalk line and screed the rest off that.

That's how the pros do it.

"self leveling" a runny 2" slab does not sound that durable, IMO
 
Last edited:
To avoid these ads, REGISTER NOW!
Top Bottom