MaverickH1
Member
Hello all. My wife and I are building a 40'x52' shop all by ourselves. Before digging we mapped out the septic system and laid the building out so it would be at least 10' away from the septic system per the requests of the local health department.
The septic system was on the right side of the building, shown on the drawing to send lines from the distribution box perpendicular to the house until it turned 90 degrees to the drain field which ran parallel to the house. We made the workshop layout so that the front of it was parallel with the house, so the septic lines should have run evenly next to it.
Well, to make a long story short, the drawings were not correct. The lines actually angle out of the distribution box. I found this out while digging my back/right corner and breaking a pipe.
I'm trying to fully assess the situation, but it looks like the attached picture is the way the system ACTUALLY goes. The yellow line on the ground is the measuring tape which marks the path. Looks like the distribution box is located at that piece of rebar in front of the tree to the left.
So now I'm left with what I see are 3 choices:
1) Move the building - this would create a lot of problems for us.
2) Move the septic system - doable... MAYBE. But I don't want the project to wait for it. The septic system has the capacity for 3 bedrooms and at the moment it's just the two of us in the house. Capping off one of 5 or 6 drain field lines should be fine so that we can pour the concrete now.
3) Change the building foundation to miss this one pipe, possibly add extra bracing to this one column.
I have found nothing in actual code that requires this pipe to be 10' away from the building. At the moment, I'm leaning towards taking that one footer/column deeper so that the footer goes below the pipe and the pipe ultimately rests on top of the footer. I just don't know if there's any real concern of breaking that pipe with building/foundation horizontal loading.
In any case... I'm looking for ideas. We were hoping to pour concrete Tuesday, but it looks like that will have to be on hold again.
The septic system was on the right side of the building, shown on the drawing to send lines from the distribution box perpendicular to the house until it turned 90 degrees to the drain field which ran parallel to the house. We made the workshop layout so that the front of it was parallel with the house, so the septic lines should have run evenly next to it.
Well, to make a long story short, the drawings were not correct. The lines actually angle out of the distribution box. I found this out while digging my back/right corner and breaking a pipe.
I'm trying to fully assess the situation, but it looks like the attached picture is the way the system ACTUALLY goes. The yellow line on the ground is the measuring tape which marks the path. Looks like the distribution box is located at that piece of rebar in front of the tree to the left.
So now I'm left with what I see are 3 choices:
1) Move the building - this would create a lot of problems for us.
2) Move the septic system - doable... MAYBE. But I don't want the project to wait for it. The septic system has the capacity for 3 bedrooms and at the moment it's just the two of us in the house. Capping off one of 5 or 6 drain field lines should be fine so that we can pour the concrete now.
3) Change the building foundation to miss this one pipe, possibly add extra bracing to this one column.
I have found nothing in actual code that requires this pipe to be 10' away from the building. At the moment, I'm leaning towards taking that one footer/column deeper so that the footer goes below the pipe and the pipe ultimately rests on top of the footer. I just don't know if there's any real concern of breaking that pipe with building/foundation horizontal loading.
In any case... I'm looking for ideas. We were hoping to pour concrete Tuesday, but it looks like that will have to be on hold again.
