Well-known member
I am in the process of backfilling to prep for my slab. I have to bring up the grade 2' on average.
I need to set my main drain pipe and toilet before I have my finished grade. What height should I have this pipe set at? Should it be cast in the concrete? Or a certain depth below? What height should it exit the building to the septic or storage tank?
I didn't sleeve the walls when pouring the foundation so I have to core a hole where I need to go. I knew this when we were forming.
Should I also bring my electrical in under the slab? I planned on bringing it up outside the wall along with my gas piping.
I need to set my main drain pipe and toilet before I have my finished grade. What height should I have this pipe set at? Should it be cast in the concrete? Or a certain depth below? What height should it exit the building to the septic or storage tank?
I didn't sleeve the walls when pouring the foundation so I have to core a hole where I need to go. I knew this when we were forming.
Should I also bring my electrical in under the slab? I planned on bringing it up outside the wall along with my gas piping.