Should a wall be placed so that the sheathing overlaps the foundation or is flush with the foundation? If the sheathing overlaps the foundation, it seems like this would cause a couple of issues. First, I would need to order my trusses to account for this difference. Second, when I install door trim, there will be a space between the trim and the foundation the width of the sheathing. What is the general practice?
 
To avoid these ads, REGISTER NOW!

southernfriedcj

Well-known member
Joined
Dec 28, 2005
Messages
421
Location
Athens, GA
We always run the edge of the wall framing to the edge of the slab so the osb sticks out 1/2" past the edge of the slab.
Basically frame the house per the plan and then add the sheathing. The trusses are ordered by the plan as well so the sheathing goes over the (floor)trusses as well.
The first floor walls are sheathed after raising them the second floor walls are squared up on the floor, sheathed and then raised.
 

kbs2244

Well-known member
Joined
Nov 11, 2006
Messages
14,065
You don't want the very outside surface of the wall to be flush with the foundation.
You want the drip edge to be at least 1/2 inch outside.
In termite country they use a metal flashing to stop them from getting to the wood, but it also serves as a drip edge.
 
To avoid these ads, REGISTER NOW!
OP
C

central1ny

Well-known member
Joined
Feb 22, 2009
Messages
134
So if the OSB overhangs by 1/2", how do you finish door trim? Seems like there would be a gap between the trim and the foundation
 

blkhonda1991

Well-known member
Joined
May 20, 2008
Messages
608
Location
Connecticut
hopefully this clears up your questions