I have a shop that’s 40’x18’ 1-12 pitch slanted down long side to long side. The ceiling/roof is 12” wood I-joist 24” on center slanted long side to long side. The wood I-joists are about 21’ including the vented roof eaves. The roof is decked with OSB vapor barrier and corrugated metal. I already have the 2”x6” walls insulated with rockwool and I’d like to do the same with the ceiling/roof.
Now to my question:
DoI need to leave an air gap between the bottom of the OSB deck and the rockwool insulation? My city code says I can just fill the whole ceiling gap with insulation but the people at rockwool said I should leave a cap between the roof deck and rockwool insulation. I live in Albuquerque and the climate is high desert/fairly dry.
Now to my question:
DoI need to leave an air gap between the bottom of the OSB deck and the rockwool insulation? My city code says I can just fill the whole ceiling gap with insulation but the people at rockwool said I should leave a cap between the roof deck and rockwool insulation. I live in Albuquerque and the climate is high desert/fairly dry.