ddawg16
Well-known member
Well....the contractor called and said he is ready for inspection prior to the concrete pour on my 20' x 25' garage floor.....
He is doing a single pour....Is this ok?
When I would getting quotes, most of the contractors said they were going to do two pours....first the footing and stem wall and then come back and do the slab.
Tomorrow is a holiday so it will be Wed before the inspector comes out....should I assume all is well if he gives it his blessing?
And yes, I do plan to keep it wet and covered for 5-7 days to allow for slow proper drying...
He is doing a single pour....Is this ok?
When I would getting quotes, most of the contractors said they were going to do two pours....first the footing and stem wall and then come back and do the slab.
Tomorrow is a holiday so it will be Wed before the inspector comes out....should I assume all is well if he gives it his blessing?
And yes, I do plan to keep it wet and covered for 5-7 days to allow for slow proper drying...


..........