Hi all, was hoping for some input. Sort of a noob to shed building and trying to put up an 8x12 on skids. I'm in the midwest and best I can tell (no clear cut answer beating google to death) the frost line's around 20" or less.

The plan is to create a gravel base around 6" deep (maybe an inch more or less since the ground is sloped) using 1" minus - what the guy I called for gravel said they use for crusher run/road base around here. My soil consists of little top soil with a lot of clay (unfortunately). Is this the best plan of action without pouring a solid slab or using sonotubes? Is 6" (planning to compact with a compactor) enough with a timber retaining frame and landscape cloth underneath to prevent the gravel from mixing into the clay?

Planning to use 4 4x4 pressure treated skids - would there be an issue placing them on 8x16x4" thick concrete blocks set into the gravel? Not sure how far apart to space them running the length of the 12' 4x4's - 16" apart (basically place a block, skip one, place one) or up to maybe 2 block lengths in between (32")? Some have said this will cause pressure points which cause the shed to sink, but I'm not sure if this is only when blocks alone are set directly on the ground. I know many people like the 4x6 or 6x6 skids, but I don't have access to 4x6 and 6x6x12 pressure treated are close to $40 in my area - vs 4x4x12's pressure treated which run under $15 each. 4x4's should work well enough shouldn't they?

Also I know there should be something between the 4x4 skids and the concrete blocks to prevent moisture wicking. Some just cut a piece of shingle to put underneath as a barrier, but I'm planning on a sheet metal roof and seems like a waste to buy a pack of shingles just for this. Would tar paper work? Maybe even folded over or something to double up the thickness.

Sorry for all the questions, last time I built anything like this I was in the southwest where it was nice and arid, no mushy clay to fight with and much better drainage. Dealing with humidity and clay soil definitely adds to the adventure. I just don't want to invest time and money into this only to have a pile of junk in a year or two half sunk into the ground. Thanks for any ideas or advice.
 
To avoid these ads, REGISTER NOW!

OccupantRJ

Well-known member
Joined
May 15, 2009
Messages
11,554
Location
Eastern North Carolina
Not an answer to your question, but a suggestion I have for you. Cut the skids at a 45 degree angle on the ends. Drill a 1 inch hole horizontally through each end about 12 inches from the end. With this, if you later decide to move the shed, slide a steel bar through the holes, attach a chain, hook to the lift arms on a decent size tractor, lift a little, and drive away. I have moved sheds down the paved road as far as half a mile by waiting right after a rain to help lube the asphalt. I bought land near me and this was the easiest way to move several sheds.
 
To avoid these ads, REGISTER NOW!
OP
B

brass89

Well-known member
Joined
Sep 15, 2014
Messages
240
Thanks OccupantRJ, probably a good idea in case it needs moved so it doesn't dig in.

Another question - since my soil is quite dense (mostly clay), should I consider putting some pvc pipes down, ends open and maybe some perforations. Have them laying at a slight slope, then put timbers over top for a retainer, then add gravel? I know the gravel is to compact and form a stable (non sinking) base with good drainage. Maybe give the water someplace to go, rather than just end up with a gravel filled swimming pool. This way if the water drains down through the rock, hits bottom and can't be absorbed very well it could at least seep out the pvc drains at the bottom and run out.
 
To avoid these ads, REGISTER NOW!