Kangaroo ID
Member
My 40x48 pole building was recently finished, now im prepping for the slab. I will be pouring it my self with the help of a couple helpers. My question is what to do with the finished height of the slab. The building has commercial girts, they lay flat between the posts. The lowest girt is a treated 2x6 with another 2x6 as the skirt board just inside of the siding but still between the posts. It seems that if the slab is poured tightly up against the bottom of the first girt it could try to lift the entire structure if the slab heaves in the winter, (N. Idaho gets a decent amount of cold) maybe I am over thinking it and an interior slab wont lift like that? Or should i hold the slab down an inch or two from the bottom of the girt board to give thing some room to move