My garage is in process.
The plan for the walls is to lay 2 rows wide, 3 courses of brick on top of the slab (monolith) around the perimeter. Then the framing would go on top of the brick. I think there will be some sort of straps that attach the frame to the brick.
However, i'm not certain how the brick will or should be attached to the slab. There are no anchor bolts present. Is mortar between the brick and slab sufficient or should i be expecting something else there?
 
To avoid these ads, REGISTER NOW!

matt_i

Well-known member
Joined
Mar 14, 2008
Messages
10,752
Location
SE Michigan
So were it my build, I would want some rebars, L-shaped, that are cast into the slab, and fitted into the brickwork.

Before that's finalized, I would epoxy some threaded rods into the slab, going up thru the brickwork, but which eventually will hold down the wooden wall framing. Their length would have to be calculated. It would be much tougher to install those after the brickwork is installed (need to go into a ~1 foot deep hole and blow out all of the dust and concentrate the 'poxy at the bottom)
 

kbs2244

Well-known member
Joined
Nov 11, 2006
Messages
14,065
"J" bolts in the slab placed to come between the 2 rows and high enough to go through the base plate.
 
OP
T

tff

Well-known member
Joined
Dec 25, 2017
Messages
423
Location
Greer, SC
Thanks for the comments. I may not have been clear. The slab is poured and a done deal. I’m in upstate SC so not hurricanes but tropical storms risk.
 
To avoid these ads, REGISTER NOW!

BillK

Well-known member
Joined
Aug 24, 2006
Messages
9,366
Location
Beautiful Southern Maryland
What do your building codes require ? I would think that does details would have been in the permit application. I had to submit drawings with all of those details when I built mine and that was 35 years ago.
 

mm08822

Well-known member
Joined
Jan 13, 2012
Messages
6,053
Location
NJ
Really, how is it that this detail was missing during plan review?!!

You will have very little uplift resistance with brick only mortared onto smooth concrete.

Need to have j bolts embedded in the slab but it is now too late for that.

Consider 8x8x16 lintel blocks around the perimeter. This would allow you to drill rebar dowels into the slab at a 30 - 45 degree angle and tie them all together with additional horizontal rebar in the lintel voids. In the lintel voids you could place j-bolts as you fill the lintel void with concrete.

You could also form a 8" x 8" wall on to top of the slab instead of using the lintel block and just pour concrete with rebar and j-bolts as described above.
 
OP
T

tff

Well-known member
Joined
Dec 25, 2017
Messages
423
Location
Greer, SC
I talked to my county office today. In my area, slab to brick and then brick to framing with straps is acceptable per code. If i lived on the coast (of SC) it would not pass. Not the best, but it does meet code.
 

kbs2244

Well-known member
Joined
Nov 11, 2006
Messages
14,065
If the slab is already down use epoxied into drilled holes for the through bolts.

Your mason may do it for you so he can space them correctly.
 

dfiler2

Well-known member
Joined
Dec 15, 2014
Messages
2,859
Location
NW Minnesota
Have you asked the contractor? I would think the process is to do the brick work then layout the bottom wall plate and drill holes between studs then build wall, stand up then anchor through predrilled holes.
 