Beercan321
Active member
- Joined
- Jun 20, 2011
- Messages
- 39
Hi guys,
I have a question about the pouring of a new slab. Tomorrow I’m having a 30x30 slab poured for my garage. Thus far the contractor’s crew has been very friendly and answered any questions I’ve had. Unfortunately any company is only as good as their worst employees and I think I might have got the contractor’s bad employees when they were prepping the base for the slab.
2 guys showed up and put down a gravel base, tamped it down, laid a vapor barrier then rolled out wire mesh. Before they left they put a chalk line around the inside of the block wall so the cement crew knows where the top of the slab is. When I looked at the chalk line it wasn’t level. I put a bubble level on the block wall and verified it was level. I then measured from the top of the block to the chalk line. From the back of the garage to where the garage doors will be the line drops 3 ½ inches. I asked one of the guys why the line slopes. He said you want the slab to slope a little so water runs out the garage door. What?! The slab is supposed to be 5” thick. I measured from the gravel base to the chalk line and it is 5” all the way around. If they poured the slab right now it would be the correct thickness but slightly sloped. Is this normal or is this guy feeding me a line of B.S.? I assume that he didn’t level out the gravel before tamping it and it’s higher in the back of the garage then the front. He then measured 5” from the gravel base all the way around the block and by doing so the chalk line is sloped.
Should I call the contactor and cancel the pour until this is straightened out or is what these guys did correct?
Thanks for any opinions/advice!
I have a question about the pouring of a new slab. Tomorrow I’m having a 30x30 slab poured for my garage. Thus far the contractor’s crew has been very friendly and answered any questions I’ve had. Unfortunately any company is only as good as their worst employees and I think I might have got the contractor’s bad employees when they were prepping the base for the slab.
2 guys showed up and put down a gravel base, tamped it down, laid a vapor barrier then rolled out wire mesh. Before they left they put a chalk line around the inside of the block wall so the cement crew knows where the top of the slab is. When I looked at the chalk line it wasn’t level. I put a bubble level on the block wall and verified it was level. I then measured from the top of the block to the chalk line. From the back of the garage to where the garage doors will be the line drops 3 ½ inches. I asked one of the guys why the line slopes. He said you want the slab to slope a little so water runs out the garage door. What?! The slab is supposed to be 5” thick. I measured from the gravel base to the chalk line and it is 5” all the way around. If they poured the slab right now it would be the correct thickness but slightly sloped. Is this normal or is this guy feeding me a line of B.S.? I assume that he didn’t level out the gravel before tamping it and it’s higher in the back of the garage then the front. He then measured 5” from the gravel base all the way around the block and by doing so the chalk line is sloped.
Should I call the contactor and cancel the pour until this is straightened out or is what these guys did correct?
Thanks for any opinions/advice!


