Wiebster
Well-known member
I’ve had a hammer in my hand since I was three. I thought I could build my own dream shop because I couldn’t get any local contractors to get me bids. With a lot of help from GJ and on line I built the walls and got the trusses set and braced. I thought I was on my downhill leg from there on out but I was wrong. I’m getting stumped and think I need some advice from the GJ experts. Not sure where to begin…. literally. I feel like I need to prioritize a list of the things need to be completed. I also need some technical help to get this dried in before the snow flies! My bracing is the bare minimum although the trusses have been through some major thunderstorms and wind with no problems. But I really want to get the roof sheathed and shingled. For that to happen I need the rafter tails trimmed, outlookers for gable overhangs, sub fascia, and most daunting I need to build four dormers. I also need to put the attic floor in so I have something to stand on to build the dormers.
Most immediately, I need the proper order to do all of this, and then a few technical suggestions. So far I’ve trimmed the rafter tails on one eve side for a 24” soffit. I ripped a 33 degree bevel (8/12 pitch) on 2x6 for the sub fascia. I’m not exactly sure how to turn the corner and start the rake overhang. I’ve got drop chord gable trusses but I swear the drop is only 3” and not 3 1/2”. (See picture). As I add the outlookers on the rakes should I notch the top chord of the gable truss or notch the outlookers to keep the roof in plane? (both are 2x4s). There is 5’ opening between the drop chord truss and the next truss over which is a girder truss. I was planning on using 2x4 joist hangars on the girder and then span that opening with 2x4s on edge 16” oc to form the gable overhang. These 2x4 outlookers are set perpendicular to the top chord, correct? Not plumb?
When it comes to the framing in between the girders for the dormers I’m at a total loss. Should I put a ridge beam in between the peaks and run rafters down parallel to the trusses to a header? Or run my roof supports perpendicular to the girders down the trusses and double up the header at the dormer opening?
Any other suggestions are appreciated






Most immediately, I need the proper order to do all of this, and then a few technical suggestions. So far I’ve trimmed the rafter tails on one eve side for a 24” soffit. I ripped a 33 degree bevel (8/12 pitch) on 2x6 for the sub fascia. I’m not exactly sure how to turn the corner and start the rake overhang. I’ve got drop chord gable trusses but I swear the drop is only 3” and not 3 1/2”. (See picture). As I add the outlookers on the rakes should I notch the top chord of the gable truss or notch the outlookers to keep the roof in plane? (both are 2x4s). There is 5’ opening between the drop chord truss and the next truss over which is a girder truss. I was planning on using 2x4 joist hangars on the girder and then span that opening with 2x4s on edge 16” oc to form the gable overhang. These 2x4 outlookers are set perpendicular to the top chord, correct? Not plumb?
When it comes to the framing in between the girders for the dormers I’m at a total loss. Should I put a ridge beam in between the peaks and run rafters down parallel to the trusses to a header? Or run my roof supports perpendicular to the girders down the trusses and double up the header at the dormer opening?
Any other suggestions are appreciated







Last edited:




