Is having a soil compaction test completed normal for a permit requirement?
I'm in NC and currently having my land leveled for an upcoming 30x50 shop. The local permit office said I need this test completed before my permit and concrete go in.
No problem, so I thought.
No one seems to know who completes this test, not the excavation companies, not the concrete guys. It took several calls to the permit office for them to just give me a single company that could do it.
So I'm confused because everyone has buildings going up in my community but no one seems knowledgeable on this seemingly important first step.
I talked to the company that supposedly completes the test but even they seemed like it was odd that I was requesting it, almost like they'd never done it outside a large engineering project.
So, if this a normal thing? I still have no idea how much this is even going to cost.
I'm in NC and currently having my land leveled for an upcoming 30x50 shop. The local permit office said I need this test completed before my permit and concrete go in.
No problem, so I thought.
No one seems to know who completes this test, not the excavation companies, not the concrete guys. It took several calls to the permit office for them to just give me a single company that could do it.
So I'm confused because everyone has buildings going up in my community but no one seems knowledgeable on this seemingly important first step.
I talked to the company that supposedly completes the test but even they seemed like it was odd that I was requesting it, almost like they'd never done it outside a large engineering project.
So, if this a normal thing? I still have no idea how much this is even going to cost.