Some Rust Bullet Application Changes

Garage Flooring

ALLIANCE MEMBER
Joined
May 21, 2011
Messages
5,288
Location
Grand Junction, CO
We are updating our site to go along with some information we are receiving form the manufacturer.

  • Maximum installation humidity levels now 90%
  • Recoat time now 2-6 hours
  • Maximum recoat time 12 hours

This is their guidelines...... I would be really careful before starting a large project in high humidity or walking on a floor that was coated 2 hours ago to put a second coat on.....

My take on it is humidity should be in the 70's and 4-6 hours, sometimes 8. Ultimately they and I will tell you the same thing. The best thing you can do is re-coat that floor as soon as you can touch it with a gloved hand and not have any transfer.
 