Good Afternoon All,
I have a SPA Wiring Project and wanted to run my plans by GJ Experts.
I have a 400 amp service consisting of 2 200 amp panels feed from a Generac 400 amp ATS.
My plan is the following starting from my panel to the SPA.
The reason for running the wire from the GFCI to the other outside box is for aesthetics, since the GFCI needs to be in line of site but at least 5 feet from the water. This is going on a patio, under my deck, so I have limited placement with the sliding door.
What size Non-Metallic Liquid-tight Conduit do I need for the 6/2with gnd? 1/2" or 3/4"?
I have a SPA Wiring Project and wanted to run my plans by GJ Experts.
I have a 400 amp service consisting of 2 200 amp panels feed from a Generac 400 amp ATS.
My plan is the following starting from my panel to the SPA.
[*}Eaton Type BR2- 50 50A 2-Pole Std Trip Breaker
- ~80 feet of Southwire Romex SIMPull 6/3 w/gnd (run inside the house)
- Square D QOE250GFINM 50A non-fusible, non-metallic SPA Box with GFCI (mounted outside the house, fed from back of box)
- ~35 feet of Southwire Romex SIMPull 6/2 w/gnd (run inside the house)
- Non-Metallic Outdoor Rated Box, probably single gang with cover (mounted outside the house, fed from back of box)
- Minimum Required amount of 6/2 w/gnd inside Non-Metallic Liquid-tight Conduit
The reason for running the wire from the GFCI to the other outside box is for aesthetics, since the GFCI needs to be in line of site but at least 5 feet from the water. This is going on a patio, under my deck, so I have limited placement with the sliding door.
What size Non-Metallic Liquid-tight Conduit do I need for the 6/2with gnd? 1/2" or 3/4"?