I'm getting ready to start the installation of a Kohler standby generator with whole house automatic transfer switch (ATS)
My electric service is underground and after arriving in my basement enters a meter box and is then fed into my main breaker panel.
In practice, the ATS needs to connect between the meter and my existing panel, thereby allowing either generator or utility power to be delivered to the house.
Due to the location of the existing panel (it is connected to the meter socket by way of a 1 inch long hub) I cannot readily locate the ATS between meter and panel.
Is it to code to run the feed from the meter socket through the existing panel and into the ATS. (i.e. can I use the existing panel as a conduit for feeding the meter (utility) conductors?)
If not, the alternative would be to use one of the knockouts on the meter panel to run a seperate conduit run, which is not the end of the world. Going through the existing panel, however, would result in a cleaner install.
What I'm looking to do is
ATS <-> CB panel <-> Utility meter
where the utility meter run would go through the CB panel and into the ATS
Hopefully this makes sense as explaining it in print is not as easy as a sketch.
Vin
My electric service is underground and after arriving in my basement enters a meter box and is then fed into my main breaker panel.
In practice, the ATS needs to connect between the meter and my existing panel, thereby allowing either generator or utility power to be delivered to the house.
Due to the location of the existing panel (it is connected to the meter socket by way of a 1 inch long hub) I cannot readily locate the ATS between meter and panel.
Is it to code to run the feed from the meter socket through the existing panel and into the ATS. (i.e. can I use the existing panel as a conduit for feeding the meter (utility) conductors?)
If not, the alternative would be to use one of the knockouts on the meter panel to run a seperate conduit run, which is not the end of the world. Going through the existing panel, however, would result in a cleaner install.
What I'm looking to do is
ATS <-> CB panel <-> Utility meter
where the utility meter run would go through the CB panel and into the ATS
Hopefully this makes sense as explaining it in print is not as easy as a sketch.
Vin