hellspcangel911
Well-known member
- Joined
- Jan 3, 2010
- Messages
- 237
Hi All,
Still in the process of building a steel barn and ran into two issues that I cant quite find an answer for. The door and window openings are framed out with 4" x 6" Cee profile steel jambs and my wall sheeting has high ribs that are .85" deep.
1. When I install the insulation it gets sandwiched between the structure and and the exterior sheeting. How do I install or flash it around the windows? My windows have a 1 3/8" flange, do I install that directly to the jamb with some flashing behind it, then run the insulation under the flashing and J-channel over the flange? I'm not sure how thick the R-15 (4") fiberglass will compress to and if the windows will need to be shimmed out so the Jchannel trim pieces flush everything together vs looking like the windows are recessed.
2. the door and window openings were designed to match each other, so the adjacent doors and windows had the jamb headers at the same heights. The detailer messed up and I didnt catch. The building is setup using the window rough openings and nominal door slab sizes (36"x80"). Aside from the obvious custom door option, I can go with 34" doors and move the headers up from 80" to 82". But this is is where I get confused. Would my J channel trim end at 80" or 82" - I'm trying to figure out how much to move the windows up so it all lines up. The same holds true for the 36" wide window thats supposed to be above a 36"wide door so the side jambs run plumb.
Thanks for all your help, gives me back some sanity.
Still in the process of building a steel barn and ran into two issues that I cant quite find an answer for. The door and window openings are framed out with 4" x 6" Cee profile steel jambs and my wall sheeting has high ribs that are .85" deep.
1. When I install the insulation it gets sandwiched between the structure and and the exterior sheeting. How do I install or flash it around the windows? My windows have a 1 3/8" flange, do I install that directly to the jamb with some flashing behind it, then run the insulation under the flashing and J-channel over the flange? I'm not sure how thick the R-15 (4") fiberglass will compress to and if the windows will need to be shimmed out so the Jchannel trim pieces flush everything together vs looking like the windows are recessed.
2. the door and window openings were designed to match each other, so the adjacent doors and windows had the jamb headers at the same heights. The detailer messed up and I didnt catch. The building is setup using the window rough openings and nominal door slab sizes (36"x80"). Aside from the obvious custom door option, I can go with 34" doors and move the headers up from 80" to 82". But this is is where I get confused. Would my J channel trim end at 80" or 82" - I'm trying to figure out how much to move the windows up so it all lines up. The same holds true for the 36" wide window thats supposed to be above a 36"wide door so the side jambs run plumb.
Thanks for all your help, gives me back some sanity.
