So I live on the flood plain in NJ, and lost most of my home to Sandy three years back.
I just finished having my home lifted, and in the process ended up with a partially collapsed ceiling.
The picture below is of my master bedroom, which opens to an attic which some previous owner converted to a loft.
While lifting the house, the old substandard main beam was replaced with a 6x14 microlam, taking all of the sag out of the house.
In the process, it lifted wall C up to where it should have been.
The ceiling in the bedroom, which is also the floor in the loft didn't move. By wall C, the ceiling was about 3" below where it should have met the wall. The ceiling is made of 2x6 on 16" centers, with a span of roughly 17' from wall a to wall B. Since the ceiling and floor above are both finished, sistering would be really time consuming and expensive.
I bought some lolly columns, and have taken the belly out of the ceiling, but now need a permanent solution.
After speaking to an engineer and a contractor friend, the consensus is to add two 4x6 microlam beams across the room and sit it on jack studs inside walls C and D.
Since I have a roughly 17' span, I was going to put 2 beams in, about 5.5' apart, diving the room into thirds. This would make each span relatively short aloowing me to get away with only 1x6 on 16" for my ceiling/loft floor.
Anybody have any input on this? I am not a contractor, but have framed out rooms and built decks before.
Just trying to get some more input from the "pros" before tearing into anothe prroject.
Thanks.
I just finished having my home lifted, and in the process ended up with a partially collapsed ceiling.
The picture below is of my master bedroom, which opens to an attic which some previous owner converted to a loft.
While lifting the house, the old substandard main beam was replaced with a 6x14 microlam, taking all of the sag out of the house.
In the process, it lifted wall C up to where it should have been.
The ceiling in the bedroom, which is also the floor in the loft didn't move. By wall C, the ceiling was about 3" below where it should have met the wall. The ceiling is made of 2x6 on 16" centers, with a span of roughly 17' from wall a to wall B. Since the ceiling and floor above are both finished, sistering would be really time consuming and expensive.
I bought some lolly columns, and have taken the belly out of the ceiling, but now need a permanent solution.
After speaking to an engineer and a contractor friend, the consensus is to add two 4x6 microlam beams across the room and sit it on jack studs inside walls C and D.
Since I have a roughly 17' span, I was going to put 2 beams in, about 5.5' apart, diving the room into thirds. This would make each span relatively short aloowing me to get away with only 1x6 on 16" for my ceiling/loft floor.
Anybody have any input on this? I am not a contractor, but have framed out rooms and built decks before.
Just trying to get some more input from the "pros" before tearing into anothe prroject.
Thanks.
