One of the sub contractors on my build is causing issues. I do have a General Contractor. However, the plumber is coming over and complaining to me about his relationship with the GC.
The conflict is caused by an issue with a broken joint for the drain under the slab. The plumber refuses to accept responsibility and is delaying the build. He has told me he will put a lien on my house, etc... If the GC does not pay him.
It's in the contract to get a lien release before final payment is made. I know I am covered there, but don't what other steps I should take before this turns into a mess. I tend to agree with the GC on this one, but how ugly can this get?
Anyone experience this before? Any pointers?
-Eric
The conflict is caused by an issue with a broken joint for the drain under the slab. The plumber refuses to accept responsibility and is delaying the build. He has told me he will put a lien on my house, etc... If the GC does not pay him.
It's in the contract to get a lien release before final payment is made. I know I am covered there, but don't what other steps I should take before this turns into a mess. I tend to agree with the GC on this one, but how ugly can this get?
Anyone experience this before? Any pointers?
-Eric