sammm
Well-known member
I think I've covered my bases.
Getting ready to pour the slab for my new garage and want to have my electrical service path ready. It will have a 100-amp sub-panel fed from the main house panel (200-amps). I plan to put the wires in PVC once they exit the soffitt and trench them (18" deep). The wires will run approx. 25' across the attic, exit thru the soffit and down an exterior wall to a trench. (See red-line in picture). The trench will be approx. 13' across to the new garage and then I'm adding another 5' to run up to the new sub-panel. Total wire run will be ~53'. (I'll round up to 55' or 60')
I'm using a UFER ground (CEE). You can barely see it in the picture. It's 5/8" rebar wire tied to more 5/8" rebar that's part of the slab footing/beam. I'm still not positive where this ground and the ground from the main panel connect to, but that's still a bit down the road.
I know I need 4-wires from the house panel (H-H-N-G). My question is what size wires do I need to use? I've been reading and I think the hots and neutral should be #3 copper. The ground should be #8. Is that right?
I plan to use 1.25" PVC, or is that too small? I also plan to add another PVC run for future use (phone, cable, etc.) Should I have it far enough way so it's in a different wall cavity from the electric? They will both be stubbed up thru the bottom plate.
Thanks in advance for the help.
Getting ready to pour the slab for my new garage and want to have my electrical service path ready. It will have a 100-amp sub-panel fed from the main house panel (200-amps). I plan to put the wires in PVC once they exit the soffitt and trench them (18" deep). The wires will run approx. 25' across the attic, exit thru the soffit and down an exterior wall to a trench. (See red-line in picture). The trench will be approx. 13' across to the new garage and then I'm adding another 5' to run up to the new sub-panel. Total wire run will be ~53'. (I'll round up to 55' or 60')
I'm using a UFER ground (CEE). You can barely see it in the picture. It's 5/8" rebar wire tied to more 5/8" rebar that's part of the slab footing/beam. I'm still not positive where this ground and the ground from the main panel connect to, but that's still a bit down the road.
I know I need 4-wires from the house panel (H-H-N-G). My question is what size wires do I need to use? I've been reading and I think the hots and neutral should be #3 copper. The ground should be #8. Is that right?
I plan to use 1.25" PVC, or is that too small? I also plan to add another PVC run for future use (phone, cable, etc.) Should I have it far enough way so it's in a different wall cavity from the electric? They will both be stubbed up thru the bottom plate.
Thanks in advance for the help.