hockey88fan
Well-known member
- Joined
- May 25, 2011
- Messages
- 428
I searched the site and didn't find what I was looking for so I'll ask the question I have and hope for an answer. I tamped the interior of my garage along the stem wall where we had back filled with the shale soil that was there. I'm using a Wacker jumping jack gas powered tamper, let me tell you that thing really has some power and is a bear to handle, my hats off to those guys who have to wrestle with that machine all day. Anyhow, along the stem wall it compacted the shale so tight that it drop the soil elevation a good 3 to 4" along the stem wall. My question is should I fill with more shale and tamp again or can I just fill the lower portion along the wall with the 2b clean stone I'm using for the base? In other words I am putting roughly 4" of this stone as a base for my pour but along the walls it would be about 7 to 8" of this stone. Thanks!!