First off, let me apologize for the lack of updates. As I mentioned in my last post, I've lost my crew to paying work and progress has been limited to what I can get manage by myself. In addition, days are getting shorter and it seems like its always too dark to take pictures by the by the time I get something done.
With that said, let me bring you up to date. We've completed the vapor barrier, rigid insulation and radiant tubing for the garage slab.
As is my habit, I employed overkill when it comes to the reinforcing; #4's at 12" centers. No real justification. I just can't seem to help myself.
Here's the lift. You can see the vapor barrier, which I took great pains to install as thoroughly as possible. I'm sure there's still some water in the pit and I don't want problems with any future floor installation.
You can also see the 'light buckets' I installed for future floor lights under the lift. I got the idea on from ODIS here on GJ. It was a pain but I didn't want to miss the opportunity.
Heres a closer shot of the light buckets. We haven't selected any of the floor lights so I needed to come up with a way to rough them in. I used 6" corrugated drainage pipe and drilled it to accept male adapters for the sched. 40 conduit. I'll grout the actual lights in when the time comes. Since we aren't going to have any exposed concrete floors, it should work fine.
Here's a shot of some buckets for floor lights that will wash an architectural concrete wall in the corridor from the garage to the house;
Some of the lights we are considering require 7" of depth. I actually had to chip down into the top of the footing an inch to provide the necessary space.
All the red tape you see is
Stego tape that comes with the 15 mil vapor barrier. It sticks like crazy.
Here's how we are handling the garage door openings. We're leaving 2" of rigid as a thermal break flush with the inside face of the wall. I'll pour a sloped apron to the outside.
With the prep work complete, we placed the slab. Since my guys were busy I had to use a sub. Since we give this guy a ton or work, I expect he'll use me right. His guys were definitely working hard to do a good job for me.
1,200 square feet requiring about 25 cy with all the haunches and thickened sections. I ordered a 4,000 psi mix with no air and a mid range, which gave us a nice 5" slump with minimal water. Overkill? Who me?.
As the concrete set, we removed the supports for the lift lights to allow the finishers better access. The buckets tried to float on us so we utilized a high tech solution - rocks.
When the concrete set a little further, we removed the supports for the lift itself.
We were very careful to finish to the proper point on the lift. Prominent warnings all over the place advise you to do so or void the warranty. I assume it has something to do with making sure water can't find it's way into the lift mechanism. You can see the light layout a little more clearly.
Given the warm temps, insulation underneath and rich mix, we had the machines on in no time.
Kind of hard to see but I set the floor drains 1 1/4" low. The slope side to side is about 6' and its closer to 10' in each direction the long way. The goal is to have water dropping off our vehicles run underneath to the drain.
After the guys cut a few control joints I covered the slab with curing fabric.
Next up is the house slab, which has even more detail. I'll probably be a month getting it ready. I'm just kidding about the time but I will try to post updates more regularly.