Now back to our regularly scheduled program: Solar Installation.
This solar company is making our install into the longest in history! It's now been a month since they started!
Friday the installers couldn't quite finish. They didn't have enough tile so the mis-match color won't show. I showed them an unseen roof area they could remove tile - CAREFULLY! - and use them where they'll be seen, then replace them with the the non-color matching ones.
I spoke to their supervisor and was assured they'd be back on Monday (today) to finish. Said he'd call the scheduler and the guy who releases the crews. Nope, they didn't show up! And I couldn't get the supervisor on the phone either, left multiple messages til his voice mail was full.
The guys that do the roof work aren't the same as the electricians that do the connection work. All the guys are nice as can be and do good work but the salesmen say ANYthing to get signatures on paper (
"...our installers have 'special shoes' so they won't break lightweight concrete tile" - I rolled my eyes). Apparently the supervision isn't a lot better. Or they just have too much work or some damn thing. If they'd said we'll be there Wednesday I'd have been fine with it as long as it doesn't rain. (Fat chance in CA these days)
Anyway, even the below electrical work didn't get done because our panel didn't have a knockout and they didn't have the punch to install an LB where they needed it. The 3 boxes are transformers that change DC into AC and send it to the house panel through the new sub panels they installed. No idea why two of them.
We'll see when they get back! Sheesh, I'm REAL tired of dealing with the clowns in their office.