Trusses are set. Now for the 60+ sheets of roof sheathing then on to walls. After a good long day of walking trusses I need a day off . . . . But, no rest for the weary. Trying to be sheathed this weekend.

Moving along.

Dan
 

Attachments

  • 78.jpg
    78.jpg
    38.3 KB · Views: 218
  • 79.jpg
    79.jpg
    27.4 KB · Views: 179
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
So after a long weekend the sheathing is 95%; just gable ends to go. Have felt on the roof until metal gets here; just glad to have this part behind me! More soon -

Dan
 

Attachments

  • 82.jpg
    82.jpg
    30.2 KB · Views: 176
  • 83.jpg
    83.jpg
    28.5 KB · Views: 228
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
Another update. Sheathing complete, roof is installed, house wrap is on, and the 10x10 doors are installed. Need to get an entry door installed, finish the soffit and hang my siding and i'll be done. Well, all but electrical, that is. Electrical starts next week.

Thanks for looking.

Dan
 

Attachments

  • 90.jpg
    90.jpg
    32.8 KB · Views: 117
  • 90 (2).jpg
    90 (2).jpg
    19 KB · Views: 128
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
More progress. Electrical service is roughed in (200a service, overhead) and the tool crib/lock-up is framed in. Hope to have power this week and then more to follow. Still haven't made the final decision on siding yet; leaning towards metal now.

Thanks for looking.

Dan
 

Attachments

  • 93.jpg
    93.jpg
    31.4 KB · Views: 124
  • 92.jpg
    92.jpg
    26.1 KB · Views: 175
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
So continuing along. Should finish up siding before too long and be done for a while. Wiring is finished, insulation and interior OSB about 1/3rd complete. Move from the old shop is in progress, so I hope to be back on other projects before the end of May. Finally!

Dan
 

Attachments

  • shop area.jpg
    shop area.jpg
    27.1 KB · Views: 285
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
Still making progress slowly but surely.

On the electrical side, all that is left to accomplish is exterior floods and interior fluorescent lighting. Right now, soffits / eave work in progress to get the siding and exterior 100%. Took and overhead shot to show the clutter of getting moved in!

Dan
 

Attachments

  • overhead.jpg
    overhead.jpg
    22.8 KB · Views: 218
To avoid these ads, REGISTER NOW!
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
Exterior almost complete. Plans are still metal siding on the south, west and north side. Hardee on the east (around the doors, facing the road).

Dan
 

Attachments

  • 98.jpg
    98.jpg
    28.4 KB · Views: 83
  • 99.jpg
    99.jpg
    30.9 KB · Views: 92
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
Exterior is almost complete; finally! Won't be long and all we'll need is paint.

Dan
 

Attachments

  • 101.jpg
    101.jpg
    27.8 KB · Views: 77
  • 102.jpg
    102.jpg
    20.6 KB · Views: 81
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
A few minor pieces of trim left to paint and we'll be done with the exterior. Already a "working" shop inside; that's never really finished, is it?

Dan
 

Attachments

  • 103.jpg
    103.jpg
    26.4 KB · Views: 104
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
So it's been quite a while since I posted an update, but the Falcon shop is, for all intents and purposes, complete. I have a few loose ends to tidy up here and there, but it'll always be that way, won't it? Finally poured my apron in the early spring, so construction is over.

Finally.

Time to play now!

Dan

Fairly cluttered while moving in. Lots more room now.

Apron poured. Really made the shop feel complete.

One of the toys relaxing on the new apron.
 

hake

Active member
Joined
Oct 5, 2009
Messages
34
So it's been quite a while since I posted an update, but the Falcon shop is, for all intents and purposes, complete. I have a few loose ends to tidy up here and there, but it'll always be that way, won't it? Finally poured my apron in the early spring, so construction is over.



Finally.



Time to play now!



Dan



Fairly cluttered while moving in. Lots more room now.



Apron poured. Really made the shop feel complete.



One of the toys relaxing on the new apron.




Looks great, would you care to share your cost for the shell and concrete please? I am looking to do the same type of build and trying to compare to a pole barn. Thanks!


Sent from my iPhone using Tapatalk
 
OP
B

big_dan

Well-known member
Joined
Dec 6, 2014
Messages
59
Location
Tennessee
It would take a while to break it all out, but to date, all included, I'm in it approximately $28k. That's only paying labor to finish the interior slab and form/pour the exterior slab. All other labor by yours truly. Hope this helps.