Hi
I got two quotes to dig up my yard for a foundation wall and to stub in floor drains, sewer and water (sewer and water are already at the location...just not at the exact spot) for my garage...
They are significantly different...
One quote was "not to exceed" $3500...if it's less I pay less...if it's more they eat the cost
The other was an estimate for $1800...that would go up if something unexpected comes up.
Both companies highly recommended in the community...the higher number comes from the "big" company...the smaller number comes from the somewhat "little" guy...
That's a huge difference but i understand they are two different types of quotes...
What might be some of the "unexpected" things that could come up that would significantly drive up the cost for the little guy?
Do I go back and ask the big company for an estimate rather than a not to exceed bid? Or is that bad practice after I asked for the not to exceed bid in the first place? the little guy doesn't do a not to exceed bid...
Thanks!
Patrick
I got two quotes to dig up my yard for a foundation wall and to stub in floor drains, sewer and water (sewer and water are already at the location...just not at the exact spot) for my garage...
They are significantly different...
One quote was "not to exceed" $3500...if it's less I pay less...if it's more they eat the cost
The other was an estimate for $1800...that would go up if something unexpected comes up.
Both companies highly recommended in the community...the higher number comes from the "big" company...the smaller number comes from the somewhat "little" guy...
That's a huge difference but i understand they are two different types of quotes...
What might be some of the "unexpected" things that could come up that would significantly drive up the cost for the little guy?
Do I go back and ask the big company for an estimate rather than a not to exceed bid? Or is that bad practice after I asked for the not to exceed bid in the first place? the little guy doesn't do a not to exceed bid...
Thanks!
Patrick